6526-6528 S 6TH AVE 90043
Certificate Information: 6526-6528 S 6TH AVE 90043
- Application / Permit
- 22016-10000-31759
- Plan Check / Job No.
- B22LA21022
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 2-STORY DETACHED 2-CAR GARAGE AND STORAGE AREA TO (N) ACCESSORY DWELLING UNIT AND STORAGE AT GROUND FLOOR PER CA GC 65852.2(e)(1)(A). UNIT AT 2ND FLOOR TO REMAIN, NOT IN SCOPE. (E) 8' X 28' CARPORT TO BE REMOVED. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 5/31/2023
- Issuing Office
- Current Status
- CofO Issued on 2/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2022 | VIVIAN LAO |
| Corrections Issued | 10/27/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 1/27/2023 | MADISON ODELL |
| Applicant returned to address corrections | 2/13/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/1/2023 | MADISON ODELL |
| Plan Check Approved | 3/10/2023 | MADISON ODELL |
| Issued | 5/31/2023 | APPLICANT |
| CofO in Progress | 2/7/2024 | ENRIQUE MIRELES |
| No Progress | 2/19/2024 | DEROLD HAUFF |
| CofO in Progress | 2/19/2024 | DEROLD HAUFF |
| Permit Finaled | 2/20/2024 | DEROLD HAUFF |
| CofO Issued | 2/20/2024 | DEROLD HAUFF |
| Permit Finaled | 2/20/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/7/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2022 | STEVE MELGAR |
| Address approval | Cleared | 12/30/2022 | JEANETTE VONG |
| Tenant Habitability Plan | Cleared | 1/3/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Daniels 3a2c Construction Inc; Lic. No.: 1052545-B | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/26/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/26/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 7/26/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/26/2023 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 8/14/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/7/2023 | No Access for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/7/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 9/7/2023 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/7/2023 | No Access for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/11/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/11/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 9/11/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 9/11/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 10/4/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/19/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/31/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/31/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/8/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/8/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/8/2024 | Approved | ENRIQUE MIRELES |
| Final | 1/22/2024 | OK to Issue CofO | SABAS ALONSO |