5676 E HUB ST 90042
Certificate Information: 5676 E HUB ST 90042
- Application / Permit
- 22016-10000-31688
- Plan Check / Job No.
- B22LA20991
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN*** REMODEL SFD - NEW EXTERIOR DOORS AND WINDOWS, NEW EXTERIOR DECK, FENCE, AND SHADE TRELLIS
- Permit Issued
- Issued on 6/22/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | SINA KHOSRAVI |
| Corrections Issued | 10/25/2022 | SINA KHOSRAVI |
| Quality Review Completed | 10/26/2022 | GARO TELMI |
| Applicant returned to address corrections | 2/13/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/15/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 4/12/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/5/2023 | SINA KHOSRAVI |
| Plan Check Approved | 5/25/2023 | SINA KHOSRAVI |
| Issued | 6/22/2023 | APPLICANT |
| CofO in Progress | 9/28/2023 | ROY SPAULDING |
| No Progress | 11/16/2023 | SCOTT FINNILA |
| Permit Finaled | 1/10/2025 | DEROLD HAUFF |
| CofO Issued | 1/10/2025 | DEROLD HAUFF |
| Permit Finaled | 1/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/28/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | AMAAN MALIK |
| Grading Pre-Inspection | Cleared | 12/9/2022 | ALEXANDER HELFER |
| CPC | Cleared | 1/11/2023 | MICAELA TORRES-GIL |
| HPOZ | Cleared | 1/11/2023 | MICAELA TORRES-GIL |
Contact Information
| Architect | Worth,, Ann C; Lic. No.: NA37948 | , |
| Contractor | Dco Construction; Lic. No.: 1078972-B | , |
| Contractor | Dco Real Estate Inc; Lic. No.: 1078972-B | , |
| Engineer | Ibarra,, Marco A; Lic. No.: C74010 | 16 N MARENGON AVE STE 604 PASADENA, CA 91101 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/20/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 7/20/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 7/26/2023 | Partial Approval | AMY COLIN |
| Interior/Exterior Lathing | 8/2/2023 | Approved | CRAIG VAUGHAN |
| Special/Order Compliance | 9/6/2023 | Corrections Issued | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 9/18/2023 | Approved | ROY SPAULDING |
| Final | 9/18/2023 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 9/18/2023 | Approved | ROY SPAULDING |
| Final | 9/25/2023 | Corrections Issued | ROY SPAULDING |
| Final | 9/27/2023 | OK to Issue CofO | ROY SPAULDING |