2856-2860 S ANCHOR AVE 90064

Certificate Information: 2856-2860 S ANCHOR AVE 90064

Application / Permit
22016-10000-31511
Plan Check / Job No.
B22LA20892
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: Convert existing attached garage in the front to an JADU PER GCS 65852.2(e)(1)(A) AND 65852.22
Permit Issued
Issued on 5/9/2023
Issuing Office
Current Status
CofO Issued on 1/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/24/2022 JAHANSHAH POURHASSAN
Corrections Issued 10/25/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 2/12/2023 ALFREDO JARA
Plan Check Approved 4/13/2023 JASON JANGADA
Issued 5/9/2023 APPLICANT
CofO in Progress 1/18/2024 OGANES TARAKHCHYAN
Permit Finaled 1/22/2024 DANIEL ORRANTE
CofO Issued 1/22/2024 DANIEL ORRANTE
Permit Finaled 1/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/26/2022 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 10/31/2022 AHMED AMARRAGY
Sewer availability Cleared 11/1/2022 AHMED AMARRAGY
Grading Pre-Inspection Cleared 11/3/2022 ROBERT HUGHES
Construction near power lines Cleared 2/3/2023 RIDWAN HARDY

Contact Information

Architect , ; Lic. No.: C39073       ,
Contractor Stewart Design Build; Lic. No.: 1061387-B       ,
Engineer Kang,, Danniel; Lic. No.: S6242 1176 N KNOLLWOOD CT      ANAHEIM, CA 92801

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/15/2023 Partial Inspection CLAYTON GRAHAM
Pre-Inspection 5/18/2023 Partial Inspection CLAYTON GRAHAM
Underground Mechanical 5/30/2023 Approved JEREMY TODD
Deputy Drilled-In Anchors 6/2/2023 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 6/5/2023 Approved JESUS PINEDA
Pre-Inspection 7/5/2023 Partial Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 8/21/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Rough 8/21/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 8/21/2023 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 8/28/2023 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 8/28/2023 Approved DAVID FEILER
HVAC-Rough 8/28/2023 Approved DAVID FEILER
PLUMBING-Rough 8/28/2023 Approved DAVID FEILER
Insulation 9/7/2023 Corrections Issued CLAYTON GRAHAM
Interior/Exterior Lathing 9/7/2023 Approved CLAYTON GRAHAM
Insulation 9/13/2023 Approved CLAYTON GRAHAM
Drywall Nailing 9/22/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 9/22/2023 Not Ready for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 9/29/2023 Approved MEL KHACHATOURIAN
Shower Pan 9/29/2023 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 1/12/2024 Approved OGANES TARAKHCHYAN
Final 1/12/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 1/12/2024 Approved OGANES TARAKHCHYAN
METHANE-Final 1/12/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 1/12/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Final 1/17/2024 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 1/17/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 1/17/2024 Approved OGANES TARAKHCHYAN