1346 N STANLEY AVE 90046
Certificate Information: 1346 N STANLEY AVE 90046
- Application / Permit
- 22016-10000-31409
- Plan Check / Job No.
- B22LA20837
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- TO VERIFY (N) ADU UNDER 21016-10000-03408. COMPLY W/ SOFT-STORY ORDIANCE LAMC DIV 93. INSTALL (N) WOOD SHEAR WALLS. Certificate of Compliance for soft story shall not be issued till Certificate of Occupancy is obtained for the ADU conversion permit under 21016-10000-03408
- Permit Issued
- Issued on 1/25/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/4/2025
Permit Application Status History
| Submitted | 10/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2022 | JESSE VIDUYA |
| Corrections Issued | 10/28/2022 | JESSE VIDUYA |
| Quality Review Completed | 10/28/2022 | HANS SANTIAGO |
| Building Plans Picked Up | 10/31/2022 | APPLICANT |
| Plan Check Approved | 1/6/2023 | JESSE VIDUYA |
| Issued | 1/25/2023 | APPLICANT |
| Permit Finaled | 6/4/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/17/2023 | MICHAEL SOTO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2023 | Conditional Approval | BRUCE CAMPBELL |
| Excavation/Setback/Form/Re-Bar | 5/24/2023 | Conditional Approval | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 5/24/2023 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Wood Construction | 8/24/2023 | Conditional Approval | VAHE KELEDJIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Partial Approval | VAHE KELEDJIAN |
| Wood Frame | 8/24/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Partial Inspection | VAHE KELEDJIAN |
| Wood Frame | 8/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 4/17/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/17/2025 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/4/2025 | Permit Finaled | ERNESTO CORRAL |