4553 N SANCOLA AVE 91602

Certificate Information: 4553 N SANCOLA AVE 91602

Application / Permit
22016-10000-31225
Plan Check / Job No.
B22LA20767
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
RENOVATION TO (E) SFD W/ MINOR STRUCTURAL ALTERATIONS
Permit Issued
Issued on 11/9/2022
Issuing Office
Metro
Current Status
Permit Finaled on 9/6/2024

Permit Application Status History

Submitted 10/14/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 KHUONG TRUONG
Corrections Issued 10/20/2022 KHUONG TRUONG
Building Plans Picked Up 10/27/2022 APPLICANT
Plan Check Approved 10/31/2022 VICTOR CHEN
Issued 11/9/2022 APPLICANT
Permit Finaled 9/5/2024 JOSE AVILA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Builder'S Touch; Lic. No.: 1035015-B 1347 N PACIFIC AVE      GLENDALE, CA 91202
Engineer Zheng,, Huang; Lic. No.: C76881 3631 URQUIDEZ AVE      GLENDALE, CA 91208

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/18/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 1/25/2023 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 1/31/2023 Approved JOHN HAYES
Footing/Foundation/Slab 1/31/2023 Approved JOHN HAYES
ELECTRICAL-Rough 4/5/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/5/2023 Approved JENNIFER RABUCHIN
Gas Test 4/7/2023 Approved MISAEL ESPARZA
HVAC-Rough 4/7/2023 Corrections Issued MISAEL ESPARZA
Wood Frame 4/7/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/12/2023 Approved JENNIFER RABUCHIN
Green Building Rough 4/12/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 4/12/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 4/12/2023 Approved JENNIFER RABUCHIN
Wood Frame 4/12/2023 Approved JENNIFER RABUCHIN
Insulation 4/28/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 5/9/2023 Approved JENNIFER RABUCHIN
Shower Pan 8/29/2023 Approved JENNIFER RABUCHIN
Final 6/12/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
MERV13>=Final 6/12/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/12/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Final 6/20/2024 No Access for Inspection JOSE AVILA
MERV13>=Final 7/1/2024 Not Ready for Inspection JOSE AVILA
PLUMBING-Final 7/1/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 7/1/2024 Approved JOSE AVILA
HVAC-Final 7/9/2024 No Access for Inspection JOSE AVILA
HVAC-Final 7/10/2024 Approved JOSE AVILA
Final 9/5/2024 Permit Finaled JOSE AVILA
MERV13>=Final 9/5/2024 Approved JOSE AVILA