654 E INDIANA AVE 90291
Certificate Information: 654 E INDIANA AVE 90291
- Application / Permit
- 22016-10000-31176
- Plan Check / Job No.
- B22LA20724
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert the existing 368 Sq. Ft. rec room into a Accessory Dwelling Unit (ADU)
- Permit Issued
- Issued on 1/8/2025
- Issuing Office
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2022 | JOE VO |
| Corrections Issued | 11/2/2022 | JOE VO |
| Applicant returned to address corrections | 11/28/2022 | JOE VO |
| Plan Check Approved | 8/28/2024 | JOE VO |
| Issued | 1/8/2025 | APPLICANT |
| CofO in Progress | 9/11/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
| CofO Issued | 9/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2022 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2022 | AHMED AMARRAGY |
| Sewer availability | Cleared | 12/5/2022 | AHMED AMARRAGY |
| Specific Plan | Cleared | 9/21/2023 | EDUARDO HERMOSO |
| CZCA Dvmt Pmt/WaiverDeMinimis | Cleared | 8/23/2024 | NOAH MCCOY |
| Exemption from CZCA | Cleared | 8/23/2024 | NOAH MCCOY |
| Specific Plan | Cleared | 8/23/2024 | NOAH MCCOY |
Contact Information
| Contractor | Abraham Building & Consulting Inc; Lic. No.: 1046696-B | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/13/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/17/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 3/19/2025 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 3/21/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/15/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/2/2025 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/6/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 6/9/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/3/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/13/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 8/13/2025 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 8/13/2025 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 8/13/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 8/13/2025 | Partial Inspection | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 8/25/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 8/25/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Green Building Final | 8/25/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 8/25/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 8/25/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 8/25/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 9/10/2025 | Approved | JESUS RODRIGUEZ |
| Final | 9/10/2025 | OK to Issue CofO | JESUS RODRIGUEZ |