11626 W HESBY ST 91601
Certificate Information: 11626 W HESBY ST 91601
- Application / Permit
- 22016-10000-31080
- Plan Check / Job No.
- B22LA20646
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL ONLY TO CONVERT (E) BED TO (N) BATH ROOM NO STRUCTURAL WORK
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 7/17/2024
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | KHUONG TRUONG |
| Plan Check Approved | 10/13/2022 | KHUONG TRUONG |
| Issued | 10/14/2022 | APPLICANT |
| Permit Finaled | 7/16/2024 | RYAN SALAZAR |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/21/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/21/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 10/21/2022 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 10/21/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/27/2022 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 10/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 10/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/10/2022 | Approved | JACK KARGODORIAN |
| Insulation | 11/10/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 11/10/2022 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 11/10/2022 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 11/10/2022 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 5/1/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 5/1/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 7/10/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/10/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Final | 7/15/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 7/16/2024 | Permit Finaled | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 7/16/2024 | Approved | RYAN SALAZAR |