5370 N CANDACE PL 90041

Certificate Information: 5370 N CANDACE PL 90041

Application / Permit
22016-10000-31068
Plan Check / Job No.
B22LA20622
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT CARPORT TO (N) ADU
Permit Issued
Issued on 1/16/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 VICTOR CHEN
Corrections Issued 10/24/2022 VICTOR CHEN
Building Plans Picked Up 10/27/2022 APPLICANT
Applicant returned to address corrections 1/20/2023 LUKE GONZALES
Applicant returned to address corrections 4/13/2023 FERNANDO FLORES
Plan Check Approved 4/17/2023 FERNANDO FLORES
Issued 1/16/2025 APPLICANT
Permit Finaled 5/10/2025 DEROLD HAUFF
CofO Issued 5/10/2025 DEROLD HAUFF
Permit Finaled 5/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/31/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 10/31/2022 JEANIE LAM
Sewer availability Cleared 10/31/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/1/2022 JEANIE LAM
Construction within easement Cleared 1/11/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 1/20/2023 VICTOR CHEN
Hydrant and Access approval Cleared 4/8/2023 GILBERT URREA

Contact Information

Contractor Radd Construction; Lic. No.: 922522-B 26078 ADAMOR RD      CALABASAS, CA 91302
Engineer Wong,, Jim C; Lic. No.: C69393 PO BOX 373      GLENDORA, CA 91740

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/24/2025 Conditional Approval JOSH MEISTER
Footing/Foundation/Slab 1/27/2025 Approved BRENDAN MORELLI
PLUMBING-Rough 1/27/2025 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 2/10/2025 Approved BRENDAN MORELLI
ELECTRICAL-Rough 2/10/2025 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Approved BRENDAN MORELLI
Green Building Rough 2/10/2025 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 2/10/2025 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 2/11/2025 Approved BRENDAN MORELLI
ELECTRICAL-Rough 2/11/2025 Approved BRENDAN MORELLI
Green Building Rough 2/11/2025 Approved BRENDAN MORELLI
HVAC-Rough 2/11/2025 Conditional Approval BRENDAN MORELLI
Interior/Exterior Lathing 2/11/2025 Partial Approval BRENDAN MORELLI
HVAC-Rough 2/14/2025 Approved JOSH MEISTER
Insulation 2/14/2025 Conditional Approval JOSH MEISTER
Interior/Exterior Lathing 2/14/2025 Partial Approval JOSH MEISTER
Drywall Nailing 2/18/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 2/18/2025 Approved JOSH MEISTER
Shower Pan 2/20/2025 Approved JOSH MEISTER
ELECTRICAL-Final 3/13/2025 Approved DAVID WILLIAMS
Final 3/13/2025 Conditional Approval DAVID WILLIAMS
Green Building Final 3/13/2025 Approved DAVID WILLIAMS
HVAC-Final 3/13/2025 Approved DAVID WILLIAMS
PLUMBING-Final 3/13/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV No Gas DAVID WILLIAMS
Smoke Detectors 3/13/2025 Approved DAVID WILLIAMS
Final 4/1/2025 Conditional Approval DAVID WILLIAMS
Special/Order Compliance 5/7/2025 Approved CHARLES BOGHOSKHAN