5370 N CANDACE PL 90041
Certificate Information: 5370 N CANDACE PL 90041
- Application / Permit
- 22016-10000-31068
- Plan Check / Job No.
- B22LA20622
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT CARPORT TO (N) ADU
- Permit Issued
- Issued on 1/16/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | VICTOR CHEN |
| Corrections Issued | 10/24/2022 | VICTOR CHEN |
| Building Plans Picked Up | 10/27/2022 | APPLICANT |
| Applicant returned to address corrections | 1/20/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 4/13/2023 | FERNANDO FLORES |
| Plan Check Approved | 4/17/2023 | FERNANDO FLORES |
| Issued | 1/16/2025 | APPLICANT |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
| CofO Issued | 5/10/2025 | DEROLD HAUFF |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/31/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | JEANIE LAM |
| Sewer availability | Cleared | 10/31/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | JEANIE LAM |
| Construction within easement | Cleared | 1/11/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 1/20/2023 | VICTOR CHEN |
| Hydrant and Access approval | Cleared | 4/8/2023 | GILBERT URREA |
Contact Information
| Contractor | Radd Construction; Lic. No.: 922522-B | 26078 ADAMOR RD CALABASAS, CA 91302 |
| Engineer | Wong,, Jim C; Lic. No.: C69393 | PO BOX 373 GLENDORA, CA 91740 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/24/2025 | Conditional Approval | JOSH MEISTER |
| Footing/Foundation/Slab | 1/27/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 1/27/2025 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/10/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/10/2025 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 2/10/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 2/10/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/11/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 2/11/2025 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 2/11/2025 | Conditional Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | BRENDAN MORELLI |
| HVAC-Rough | 2/14/2025 | Approved | JOSH MEISTER |
| Insulation | 2/14/2025 | Conditional Approval | JOSH MEISTER |
| Interior/Exterior Lathing | 2/14/2025 | Partial Approval | JOSH MEISTER |
| Drywall Nailing | 2/18/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 2/18/2025 | Approved | JOSH MEISTER |
| Shower Pan | 2/20/2025 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 3/13/2025 | Approved | DAVID WILLIAMS |
| Final | 3/13/2025 | Conditional Approval | DAVID WILLIAMS |
| Green Building Final | 3/13/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 3/13/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 3/13/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV No Gas | DAVID WILLIAMS |
| Smoke Detectors | 3/13/2025 | Approved | DAVID WILLIAMS |
| Final | 4/1/2025 | Conditional Approval | DAVID WILLIAMS |
| Special/Order Compliance | 5/7/2025 | Approved | CHARLES BOGHOSKHAN |