905 E 118TH PL 90059

Certificate Information: 905 E 118TH PL 90059

Application / Permit
22016-10000-31056
Plan Check / Job No.
B22LA20611
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU CONVERSION FROM (E) GARAGE W/ ADDITION AT AREA PER LAMC 12.22 A33 (c) AND (d)
Permit Issued
Issued on 2/28/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 DANIEL SANJUAN
Corrections Issued 10/13/2022 DANIEL SANJUAN
Plan Check Approved 1/27/2023 SAMUEL GONZALEZ
Issued 2/28/2023 APPLICANT
CofO in Progress 12/17/2024 JOSEPH MCGARRY
Permit Finaled 12/18/2024 ANSON MAGLASANG
CofO Issued 12/18/2024 ANSON MAGLASANG
Permit Finaled 12/18/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/3/2023 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 1/3/2023 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 1/18/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 1/26/2023 CHRISTOPHER ROCHA
Construction near power lines Cleared 1/27/2023 WALTER RAMIREZ
Construction within easement Cleared 1/27/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/17/2023 Conditional Approval JAMES CHAVEZ
PLUMBING-Rough 5/10/2023 Approved JOHN KLARIN
PLUMBING-Rough 5/11/2023 Not Ready for Inspection JOHN KLARIN
Deputy Drilled-In Anchors 5/15/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 7/5/2023 Approved JOHN KLARIN
Pre-Inspection 10/30/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 11/3/2023 Corrections Issued JOHN KLARIN
Gas Test 11/3/2023 Approved JOHN KLARIN
PLUMBING-Rough 11/3/2023 Corrections Issued JOHN KLARIN
Rough-Elec/Plmb/HVAC 12/4/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 12/19/2023 Approved JOHN KLARIN
HVAC-Rough 12/19/2023 Approved JOHN KLARIN
Insulation 12/19/2023 Corrections Issued JOHN KLARIN
Insulation 1/2/2024 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 1/30/2024 Approved JOHN KLARIN
Drywall Nailing 1/30/2024 Approved JOHN KLARIN
Green Building Rough 1/30/2024 Approved JOHN KLARIN
MERV13>=Rough 1/30/2024 Approved JOHN KLARIN
Shower Pan 2/28/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 6/12/2024 Corrections Issued BEN MOLSTAD
Sewer 6/20/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 9/26/2024 Corrections Issued BEN MOLSTAD
Final 9/26/2024 Corrections Issued BEN MOLSTAD
Green Building Final 9/26/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 9/26/2024 Corrections Issued BEN MOLSTAD
MERV13>=Final 9/26/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 9/26/2024 Approved BEN MOLSTAD
Final 10/23/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Final 10/23/2024 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Not Ready ANTHONY EGSON
Final 11/14/2024 Corrections Issued ANTHONY EGSON
Green Building Final 11/14/2024 Partial Approval ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Approved ANTHONY EGSON
Gas Test 12/11/2024 Corrections Issued ANTHONY EGSON
Final 12/16/2024 OK to Issue CofO JOSEPH MCGARRY
Gas Test 12/16/2024 Approved JOSEPH MCGARRY
Green Building Final 12/16/2024 Approved JOSEPH MCGARRY