130 S ALVARADO ST 90057
Certificate Information: 130 S ALVARADO ST 90057
- Application / Permit
- 22016-10000-31028
- Plan Check / Job No.
- B22LA20587
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EPLAN EARLY START demolition of existing improvement (soft demo) including non structural partition walls, ceilings, & plumbing ( see comments )
- Permit Issued
- Issued on 12/9/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/10/2024
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2022 | LUKE GONZALES |
| Corrections Issued | 10/19/2022 | LUKE GONZALES |
| Applicant returned to address corrections | 10/26/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 11/8/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 11/18/2022 | SAMUEL GONZALEZ |
| Issued | 12/9/2022 | APPLICANT |
| Permit Finaled | 1/10/2024 | KATY RAMIREZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Morris,, Peter Lloyd; Lic. No.: NA32096 | , |
| Contractor | Bergman Build,Llc; Lic. No.: 982577-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/20/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 12/15/2023 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 12/15/2023 | Approved | KATY RAMIREZ |
| Final | 1/10/2024 | Permit Finaled | KATY RAMIREZ |