4755-4757 N CEDROS AVE 91403
Certificate Information: 4755-4757 N CEDROS AVE 91403
- Application / Permit
- 22016-10000-30908
- Plan Check / Job No.
- B22LA20472
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATTACHED 21'3"X23'8" GARAGE & PORTION (11'10"X21') OF EXISTING DWELLING INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e).
- Permit Issued
- Issued on 11/2/2022
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 3/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2022 | FERNANDO FLORES |
| Corrections Issued | 10/11/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 10/31/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 11/2/2022 | JESSE JIMENEZ |
| Issued | 11/2/2022 | APPLICANT |
| CofO in Progress | 3/13/2025 | JACK KARGODORIAN |
| CofO in Progress | 3/13/2025 | ROBERT GOLD |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/12/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/1/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/24/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 1/24/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/6/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 2/6/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 2/6/2023 | Approved | THOMAS FINNILA |
| Wood Frame | 2/6/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/17/2023 | Approved | THOMAS FINNILA |
| HVAC-Rough | 2/17/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/17/2023 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 2/17/2023 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 2/24/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/24/2023 | Approved | THOMAS FINNILA |
| Wood Frame | 2/24/2023 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/20/2023 | Approved | THOMAS FINNILA |
| Insulation | 3/20/2023 | Approved | THOMAS FINNILA |
| Drywall Nailing | 4/7/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Drywall Nailing | 4/25/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/15/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 5/15/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/15/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 5/15/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/14/2024 | No Access for Inspection | MISAEL ESPARZA |
| Final | 2/14/2024 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Final | 2/14/2024 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Rough | 2/14/2024 | No Access for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 2/14/2024 | No Access for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 2/14/2024 | No Access for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 2/14/2024 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/24/2024 | Not Ready for Inspection | DAVID MATSON |
| Final | 6/24/2024 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 6/24/2024 | Not Ready for Inspection | DAVID MATSON |
| Green Building Rough | 6/24/2024 | Not Ready for Inspection | DAVID MATSON |
| MERV13>=Final | 6/24/2024 | Not Ready for Inspection | DAVID MATSON |
| MERV13>=Rough | 6/24/2024 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 6/24/2024 | Not Ready for Inspection | DAVID MATSON |
| Pre-Inspection | 7/12/2024 | Partial Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 11/12/2024 | Partial Approval | JACK KARGODORIAN |
| Final | 11/12/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 11/12/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 11/12/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Final | 11/12/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Rough | 11/12/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/12/2024 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 11/12/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/14/2025 | Approved | JACK KARGODORIAN |
| Final | 1/14/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Final | 1/14/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 1/14/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 1/14/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 1/14/2025 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 1/14/2025 | Approved | JACK KARGODORIAN |
| Final | 1/17/2025 | Corrections Issued | JACK KARGODORIAN |
| Final | 1/29/2025 | Not Ready for Inspection | JACK KARGODORIAN |