3538 S REDWOOD AVE 90066

Certificate Information: 3538 S REDWOOD AVE 90066

Application / Permit
22016-10000-30761
Plan Check / Job No.
B22LA20390
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Garage conversion into an 408 sf ADU
Permit Issued
Issued on 11/22/2022
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 ARSALAN SHABESTARI
Corrections Issued 10/22/2022 ARSALAN SHABESTARI
Quality Review Completed 10/24/2022 FARUK SEZER
Plan Check Approved 11/21/2022 ARSALAN SHABESTARI
Issued 11/22/2022 APPLICANT
CofO in Progress 3/13/2023 RICHARD STEINBACH
Permit Finaled 3/15/2023 DANIEL ORRANTE
CofO Issued 3/15/2023 DANIEL ORRANTE
Permit Finaled 3/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/27/2022 STEVE MELGAR
Sewer availability Cleared 10/27/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/28/2022 STEVE MELGAR
Grading Pre-Inspection Cleared 11/17/2022 KIRK LINKLATER

Contact Information

Contractor Global Developers Inc; Lic. No.: 1023874-B       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/1/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 12/5/2022 Corrections Issued JESUS RODRIGUEZ
Gas Test 12/5/2022 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 12/5/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Not Ready for Inspection JESUS RODRIGUEZ
Special/Order Compliance 12/7/2022 Partial Inspection JEREMY TODD
BUILDING-Rough-Frame 12/22/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 12/22/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Conditional Approval JESUS RODRIGUEZ
Gas Test 12/22/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 12/22/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 12/22/2022 Approved JESUS RODRIGUEZ
Wood Frame 12/22/2022 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 12/27/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/27/2022 Approved JESUS RODRIGUEZ
Special/Order Compliance 12/27/2022 Partial Inspection CLAYTON GRAHAM
Insulation 12/30/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 1/9/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 1/9/2023 Approved JESUS RODRIGUEZ
Green Building Rough 1/9/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 3/10/2023 Approved JESUS RODRIGUEZ
Final 3/10/2023 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 3/10/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 3/10/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 3/10/2023 Approved JESUS RODRIGUEZ
Smoke Detectors 3/10/2023 Approved JESUS RODRIGUEZ