5164 W SUNLIGHT PL 90016
Certificate Information: 5164 W SUNLIGHT PL 90016
- Application / Permit
- 22016-10000-30697
- Plan Check / Job No.
- B22LA20375
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN 2) GARAGE CONVERSION TO ADU
- Permit Issued
- Issued on 12/6/2022
- Issuing Office
- Current Status
- CofO Issued on 3/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | NGHI SU |
| Corrections Issued | 10/15/2022 | NGHI SU |
| Quality Review Completed | 10/20/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/21/2022 | NGHI SU |
| Plan Check Approved | 11/29/2022 | NGHI SU |
| Issued | 12/6/2022 | APPLICANT |
| CofO in Progress | 2/27/2025 | ARTHUR NEGRETE |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
| CofO Issued | 3/2/2025 | DEROLD HAUFF |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 11/2/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 11/2/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Irene Gailen; Lic. No.: C68382 | 3411 CAROLINE AVE CULVER CITY, CA 90232 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2023 | Conditional Approval | JOSE AVILA |
| PLUMBING-Rough | 2/13/2023 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 2/13/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 2/15/2023 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 2/15/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 3/3/2023 | Corrections Issued | JOSE AVILA |
| Deputy Drilled-In Anchors | 3/10/2023 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 3/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/16/2023 | Partial Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 3/31/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 3/31/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 4/17/2023 | No Access for Inspection | JOSE AVILA |
| HVAC-Rough | 4/17/2023 | No Access for Inspection | JOSE AVILA |
| PLUMBING-Rough | 4/17/2023 | Order to Comply Issued | JOSE AVILA |
| ELECTRICAL-Rough | 4/24/2023 | Partial Inspection | JOSE AVILA |
| HVAC-Rough | 4/24/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/24/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 7/7/2023 | Conditional Approval | JOSE AVILA |
| HVAC-Rough | 7/7/2023 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 7/7/2023 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 7/18/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 7/18/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 7/18/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/7/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 8/18/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/18/2023 | Approved | JOSE AVILA |
| Special/Order Compliance | 8/18/2023 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 9/20/2023 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 9/21/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 10/2/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 4/1/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/2/2024 | Approved | RICHARD DOCKUS |
| HVAC-Final | 8/20/2024 | Approved | ARTHUR NEGRETE |
| Gas Test | 11/13/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 11/13/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 11/19/2024 | Corrections Issued | ARTHUR NEGRETE |
| ELECTRICAL-Final | 12/10/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 12/10/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/23/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 12/23/2024 | Approved | ARTHUR NEGRETE |
| Final | 12/27/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 12/27/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 12/27/2024 | Approved | ARTHUR NEGRETE |
| Final | 2/26/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Special/Order Compliance | 2/26/2025 | Partial Inspection | ALEX COLIN |