7343 W 89TH ST 90045
Certificate Information: 7343 W 89TH ST 90045
- Application / Permit
- 22016-10000-30687
- Plan Check / Job No.
- B22LA20363
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Conversion of existing detached garage into an ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 1/25/2023
- Issuing Office
- Current Status
- CofO Issued on 10/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2022 | RAHEL BEYENE |
| Corrections Issued | 10/17/2022 | RAHEL BEYENE |
| Applicant returned to address corrections | 1/19/2023 | RAHEL BEYENE |
| Plan Check Approved | 1/24/2023 | ADAM HEGAZI |
| Issued | 1/25/2023 | APPLICANT |
| CofO in Progress | 10/13/2023 | BOBBY KEY |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| CofO Issued | 10/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2022 | AHMED AMARRAGY |
| Sewer availability | Cleared | 11/1/2022 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2022 | AHMED AMARRAGY |
| Construction near power lines | Cleared | 1/17/2023 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 1/24/2023 | RAHEL BEYENE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christenson,, Paul Scott; Lic. No.: C57182 | 3529 COASTVIEW CT CARLSBAD, CA 92010 |
| Engineer | Christenson,, Paul Scott; Lic. No.: NA57182 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/5/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/5/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 4/5/2023 | Partial Approval | BOBBY KEY |
| Sewer | 4/5/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 4/21/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/28/2023 | Approved | KENNETH NAGLE |
| Green Building Rough | 4/28/2023 | Approved | KENNETH NAGLE |
| Insulation | 4/28/2023 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 4/28/2023 | Partial Approval | KENNETH NAGLE |
| Drywall Nailing | 5/5/2023 | Approved | BOBBY KEY |
| HVAC-Final | 5/5/2023 | Corrections Issued | BOBBY KEY |
| Shower Pan | 5/31/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/6/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/26/2023 | Corrections Issued | BOBBY KEY |
| Final | 9/26/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/26/2023 | Approved | BOBBY KEY |
| HVAC-Final | 9/26/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/26/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 9/26/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/5/2023 | Corrections Issued | HERBERT GIRON |
| Final | 10/5/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 10/5/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Approved | HERBERT GIRON |
| ELECTRICAL-Final | 10/12/2023 | Approved | BOBBY KEY |
| Final | 10/12/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 10/12/2023 | Approved | BOBBY KEY |