6425 W DREXEL AVE 90048
Certificate Information: 6425 W DREXEL AVE 90048
- Application / Permit
- 22016-10000-30664
- Plan Check / Job No.
- B22LA20348
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Existing garage conversion to ADU - 475 sf Per State law and GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/20/2023
- Issuing Office
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2022 | ZAW HAN |
| Corrections Issued | 10/17/2022 | ZAW HAN |
| Applicant returned to address corrections | 1/11/2023 | ZAW HAN |
| Plan Check Approved | 1/12/2023 | ZAW HAN |
| Issued | 1/20/2023 | APPLICANT |
| CofO in Progress | 6/8/2023 | JEREMY TODD |
| Permit Finaled | 6/29/2023 | DANIEL ORRANTE |
| CofO Issued | 6/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 10/27/2022 | STEVEN WECHSLER |
| Tenant Habitability Plan | Cleared | 10/27/2022 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 11/7/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 11/7/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/7/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 1/8/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/8/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/8/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 3/8/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 3/16/2023 | Not Ready for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 3/16/2023 | Not Ready for Inspection | JEREMY TODD |
| Underground Mechanical | 3/16/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 3/17/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 3/17/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 3/20/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 3/20/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 4/4/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 4/4/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 4/4/2023 | Partial Approval | JEREMY TODD |
| PLUMBING-Rough | 4/4/2023 | Approved | JEREMY TODD |
| Wood Frame | 4/4/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Partial Approval | JEREMY TODD |
| Insulation | 4/10/2023 | Approved | JEREMY TODD |
| Insulation | 4/11/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/13/2023 | Approved | JEREMY TODD |
| Shower Pan | 4/13/2023 | Not Ready for Inspection | JEREMY TODD |
| Interior/Exterior Lathing | 4/17/2023 | Partial Approval | MICHAEL PELHAM |
| Shower Pan | 4/17/2023 | Approved | MICHAEL PELHAM |
| Shower Pan | 4/18/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 4/24/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 5/18/2023 | Corrections Issued | JEREMY TODD |
| HVAC-Final | 5/18/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 5/18/2023 | Corrections Issued | JEREMY TODD |
| ELECTRICAL-Final | 5/23/2023 | Approved | JEREMY TODD |
| Final | 5/23/2023 | Corrections Issued | JEREMY TODD |
| METHANE-Final | 5/23/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 5/23/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 5/23/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 5/23/2023 | Approved | JEREMY TODD |
| Final | 6/7/2023 | OK to Issue CofO | JEREMY TODD |
| Verify Rec and Parks Fee Memo | 6/7/2023 | Approved | JEREMY TODD |
| Verify Rec and Parks Fee Memo | 6/9/2023 | Approved | JEREMY TODD |