233-235 S AVENUE 50 90042
Certificate Information: 233-235 S AVENUE 50 90042
- Application / Permit
- 22016-10000-30610
- Plan Check / Job No.
- B22LA20323
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE AND LAUNDRY ROOM INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 10/11/2023
- Issuing Office
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/15/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 9/13/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 10/6/2023 | ROSENDO MEDINA |
| Issued | 10/11/2023 | APPLICANT |
| CofO in Progress | 1/29/2024 | AMY COLIN |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
| CofO Issued | 2/7/2024 | DEROLD HAUFF |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2023 | JEANETTE VONG |
| Sewer availability | Cleared | 2/28/2023 | JEANETTE VONG |
| HPOZ | Cleared | 8/25/2023 | MICAELA TORRES-GIL |
| Grading Pre-Inspection | Cleared | 9/18/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Santos,, Michael; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/13/2023 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 10/13/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 10/30/2023 | Partial Approval | AMY COLIN |
| Green Building Rough | 10/30/2023 | Approved | AMY COLIN |
| MERV13>=Rough | 10/30/2023 | Approved | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 10/30/2023 | Approved | AMY COLIN |
| Underground Mechanical | 10/30/2023 | Approved | AMY COLIN |
| Insulation | 11/6/2023 | Approved | AMY COLIN |
| Deputy Wood Construction | 11/7/2023 | Conditional Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 11/27/2023 | Conditional Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/27/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Shower Pan | 11/27/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 11/30/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 11/30/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 1/5/2024 | Approved | AMY COLIN |
| Final | 1/5/2024 | Corrections Issued | AMY COLIN |
| Green Building Final | 1/5/2024 | Approved | AMY COLIN |
| MERV13>=Final | 1/5/2024 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 1/5/2024 | Approved | AMY COLIN |
| Final | 1/22/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 1/26/2024 | OK to Issue CofO | AMY COLIN |