2826 E BOULDER ST 90033

Certificate Information: 2826 E BOULDER ST 90033

Application / Permit
22016-10000-30531
Plan Check / Job No.
B22LA20248
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER CA GOVT CODE 65852.2(e)(1)(A)
Permit Issued
Issued on 2/7/2023
Issuing Office
Current Status
CofO Issued on 9/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2022 APPLICANT
Assigned to Plan Check Engineer 10/12/2022 HANS SANTIAGO
Corrections Issued 10/12/2022 HANS SANTIAGO
Plan Check Approved 11/16/2022 ANDREW SANTIAGO
Issued 2/7/2023 APPLICANT
CofO in Progress 8/13/2024 OSVALDO PARAMO
Permit Finaled 9/20/2024 DEROLD HAUFF
CofO Issued 9/20/2024 DEROLD HAUFF
Permit Finaled 9/20/2024 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 10/14/2022 SPENCER WEJROWSKI
Address approval Cleared 10/17/2022 CELINA MORENO
Sewer availability Cleared 10/17/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/18/2022 CELINA MORENO
Grading Pre-Inspection Cleared 10/18/2022 KIRK LINKLATER
Hydrant and Access approval Cleared 11/12/2022 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/6/2023 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 3/6/2023 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 3/7/2023 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 3/8/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 3/8/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Partial Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 6/13/2023 Corrections Issued OSVALDO PARAMO
Shower Pan 6/13/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 6/26/2023 Partial Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 6/26/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 7/3/2023 Approved OSVALDO PARAMO
Green Building Rough 7/3/2023 Approved OSVALDO PARAMO
METHANE-Rough 7/3/2023 Approved OSVALDO PARAMO
Insulation 7/10/2023 Approved RUBEN SALAS
Interior/Exterior Lathing 7/10/2023 Approved RUBEN SALAS
Drywall Nailing 7/14/2023 Approved OSVALDO PARAMO
Sewer 10/26/2023 Not Ready for Inspection OSVALDO PARAMO
Sewer 10/27/2023 Approved OSVALDO PARAMO
Gas Test 7/11/2024 Approved OSVALDO PARAMO
ELECTRICAL-Final 7/23/2024 Approved OSVALDO PARAMO
PLUMBING-Final 7/23/2024 Approved OSVALDO PARAMO
Final 8/8/2024 OK to Issue CofO OSVALDO PARAMO
Green Building Final 8/8/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Approved OSVALDO PARAMO
Service/Power Release 8/8/2024 Approved OSVALDO PARAMO
Smoke Detectors 8/8/2024 Approved OSVALDO PARAMO