1340 1/2 S 2ND AVE 90019

Certificate Information: 1340 1/2 S 2ND AVE 90019

Application / Permit
22016-10000-30508
Plan Check / Job No.
B22LA20226
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: (N) ADU PER CA GOVT CODE 66852.3 (e_)1)(B) & APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d), (g) WITH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 12/5/2023
Issuing Office
Current Status
CofO Issued on 12/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 MAHNAZ NOURHASHEMI
Corrections Issued 11/19/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 11/30/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 10/17/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 10/31/2023 MAHNAZ NOURHASHEMI
Issued 12/5/2023 APPLICANT
CofO in Progress 12/1/2025 WILLIAM SIERRA
Permit Finaled 12/3/2025 DEROLD HAUFF
CofO Issued 12/3/2025 DEROLD HAUFF
Permit Finaled 12/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/14/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 2/17/2023 AMAAN MALIK
Sewer availability Cleared 2/17/2023 AMAAN MALIK
Hydrant and Access approval Cleared 3/6/2023 RUEL COLE
Green Code Cleared 3/31/2023 Gurunath Nesarajah
Permit Cleared 4/10/2023 THAN WIN
Community Plan Implem. Overlay Cleared 5/26/2023 KYLE WINSTON
ZI Cleared 5/26/2023 KYLE WINSTON
Community Plan Implem. Overlay Cleared 6/22/2023 TAIMOUR TANAVOLI
Low Impact Development Cleared 6/23/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 8/25/2023 STEVEN JIN
Community Plan Implem. Overlay Cleared 8/26/2023 CHRISTOPHER ROCHA
Trees in Parkway Cleared 9/12/2023 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Acciani,, Mark; Lic. No.: C83929 PO BOX 1390      RUNNING SPRINGS, CA 92382

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/30/2024 Order to Comply Issued RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 3/14/2024 Partial Approval ARTHUR NEGRETE
Underground Mechanical 3/14/2024 Partial Approval ARTHUR NEGRETE
Footing/Foundation/Slab 4/11/2024 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 4/11/2024 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Subgrade 4/11/2024 Not Ready for Inspection JOSEPH MCGARRY
Deputy Methane Barrier 5/3/2024 Partial Approval SCOTT FINNILA
METHANE-Subgrade 5/6/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/6/2024 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/21/2024 Approved WILLIAM KUEHN
METHANE-Barrier 5/21/2024 Approved WILLIAM KUEHN
Deputy Reinf. Concrete 5/28/2024 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Approved WILLIAM KUEHN
Deputy Methane Barrier 7/3/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 7/3/2024 Approved JOSEPH MCGARRY
HVAC-Rough 7/3/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/3/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/5/2024 Approved WILLIAM SIERRA
Green Building Rough 8/5/2024 Approved WILLIAM SIERRA
METHANE-Rough 8/5/2024 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 8/5/2024 Approved WILLIAM SIERRA
Underground Mechanical 8/7/2024 Approved WILLIAM SIERRA
Insulation 8/20/2024 Approved WILLIAM SIERRA
Interior/Exterior Lathing 8/20/2024 Partial Approval WILLIAM SIERRA
Drywall Nailing 8/27/2024 Corrections Issued WILLIAM SIERRA
Interior/Exterior Lathing 8/27/2024 Approved WILLIAM SIERRA
Special/Order Compliance 8/27/2024 Corrections Issued WILLIAM SIERRA
Drywall Nailing 8/28/2024 Approved WILLIAM SIERRA
Interior/Exterior Lathing 8/28/2024 Approved WILLIAM SIERRA
Service/Power Release 12/3/2024 Corrections Issued WILLIAM SIERRA
Service/Power Release 4/4/2025 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Final 6/3/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 6/3/2025 Corrections Issued WILLIAM SIERRA
Service/Power Release 6/3/2025 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Final 6/9/2025 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 6/9/2025 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 6/12/2025 Corrections Issued WILLIAM SIERRA
Final 6/12/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 6/12/2025 Approved WILLIAM SIERRA
HVAC-Final 6/12/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 6/12/2025 Corrections Issued WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Not Required WILLIAM SIERRA
Service/Power Release 6/12/2025 Approved WILLIAM SIERRA
Smoke Detectors 6/12/2025 Approved WILLIAM SIERRA
Final 8/26/2025 Conditional Approval WILLIAM SIERRA
Final 12/1/2025 OK to Issue CofO WILLIAM SIERRA