10416 W CROCKETT ST 91352
Certificate Information: 10416 W CROCKETT ST 91352
- Application / Permit
- 22016-10000-30468
- Plan Check / Job No.
- B22LA20194
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING DETACHED (E) GARAGE AND (E) STOREGE TO (N) ADU PER ODINANCE. ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 12/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | KHUONG TRUONG |
| Corrections Issued | 10/8/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 10/12/2022 | APPLICANT |
| Plan Check Approved | 10/31/2022 | FARSHAD ALIMOHAMADI |
| Issued | 12/27/2022 | APPLICANT |
| CofO in Progress | 4/28/2023 | DAVID ANDERSON |
| Permit Finaled | 5/2/2023 | MICHAEL SMITH |
| CofO Issued | 5/2/2023 | MICHAEL SMITH |
| Permit Finaled | 5/2/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2022 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | FERNANDO GIL |
| Sewer availability | Cleared | 10/12/2022 | FERNANDO GIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2023 | Corrections Issued | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 3/6/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 3/6/2023 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/13/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 3/13/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 3/13/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 3/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/20/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 3/20/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 3/20/2023 | Approved | DAVID ANDERSON |
| Wood Frame | 3/20/2023 | Approved | DAVID ANDERSON |
| Insulation | 3/24/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/24/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 3/24/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/28/2023 | Approved | DAVID ANDERSON |
| Sewer | 3/28/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 3/28/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 4/20/2023 | Approved | DAVID ANDERSON |
| Final | 4/27/2023 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 4/27/2023 | Approved | DAVID ANDERSON |
| MERV13>=Final | 4/27/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 4/27/2023 | Approved | DAVID ANDERSON |