1308 1/2 S KENISTON AVE 90019
Certificate Information: 1308 1/2 S KENISTON AVE 90019
- Application / Permit
- 22016-10000-30294
- Plan Check / Job No.
- B22LA20036
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing Garage to ADU & addition
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | PRANITA SHAH |
| Corrections Issued | 11/1/2022 | PRANITA SHAH |
| Quality Review Completed | 11/8/2022 | JOHN FRANCIA |
| Applicant returned to address corrections | 12/21/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 1/9/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 1/10/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 1/27/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 2/8/2023 | PRANITA SHAH |
| Plan Check Approved | 2/15/2023 | PRANITA SHAH |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 7/20/2024 | JOAQUIN GREENOUGH |
| CofO Issued | 7/22/2024 | DEROLD HAUFF |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 11/16/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | JEANIE LAM |
| Sewer availability | Cleared | 11/17/2022 | JEANIE LAM |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/23/2023 | Corrections Issued | CALEB MEISTER |
| METHANE-Barrier | 3/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Subgrade | 3/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| Sewer | 5/2/2023 | Partial Approval | CALEB MEISTER |
| Underground Mechanical | 5/2/2023 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 10/17/2023 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 10/17/2023 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 10/17/2023 | Approved | STUART CHAPMAN |
| Pre-Inspection | 10/19/2023 | Partial Approval | CALEB MEISTER |
| Underground Mechanical | 10/30/2023 | Partial Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 11/1/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/6/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 11/17/2023 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Partial Approval | RONNIE MINDANAO |
| HVAC-Rough | 11/17/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 11/17/2023 | Partial Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/22/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 11/22/2023 | Approved | STUART CHAPMAN |
| Shower Pan | 11/22/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/27/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 11/27/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 11/27/2023 | Approved | JUSTIN HAWLEY |
| METHANE-Rough | 11/27/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 11/27/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 11/30/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 11/30/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/30/2023 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 12/6/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 12/8/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/29/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 2/29/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Special/Order Compliance | 2/29/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 3/5/2024 | Conditional Approval | JUSTIN HAWLEY |
| Sewer | 3/14/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/19/2024 | Conditional Approval | JUSTIN HAWLEY |
| PLUMBING-Rough | 4/2/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 4/2/2024 | Partial Approval | ENRIQUE MIRELES |
| Gas Test | 4/3/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 4/12/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Ready | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 5/2/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Final | 7/11/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 7/11/2024 | Approved | JUSTIN HAWLEY |
| Green Building Final | 7/11/2024 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 7/11/2024 | Approved | JUSTIN HAWLEY |
| Final | 7/18/2024 | OK to Issue CofO | JOAQUIN GREENOUGH |