1308 1/2 S KENISTON AVE 90019

Certificate Information: 1308 1/2 S KENISTON AVE 90019

Application / Permit
22016-10000-30294
Plan Check / Job No.
B22LA20036
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert existing Garage to ADU & addition
Permit Issued
Issued on 2/16/2023
Issuing Office
Current Status
CofO Issued on 7/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 PRANITA SHAH
Corrections Issued 11/1/2022 PRANITA SHAH
Quality Review Completed 11/8/2022 JOHN FRANCIA
Applicant returned to address corrections 12/21/2022 PRANITA SHAH
Applicant returned to address corrections 1/9/2023 PRANITA SHAH
Applicant returned to address corrections 1/10/2023 PRANITA SHAH
Applicant returned to address corrections 1/27/2023 PRANITA SHAH
Applicant returned to address corrections 2/8/2023 PRANITA SHAH
Plan Check Approved 2/15/2023 PRANITA SHAH
Issued 2/16/2023 APPLICANT
CofO in Progress 7/20/2024 JOAQUIN GREENOUGH
CofO Issued 7/22/2024 DEROLD HAUFF
Permit Finaled 7/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/16/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 11/16/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/17/2022 JEANIE LAM
Sewer availability Cleared 11/17/2022 JEANIE LAM

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/23/2023 Corrections Issued CALEB MEISTER
METHANE-Barrier 3/23/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Subgrade 3/23/2023 Not Ready for Inspection CALEB MEISTER
Sewer 5/2/2023 Partial Approval CALEB MEISTER
Underground Mechanical 5/2/2023 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 10/17/2023 Corrections Issued STUART CHAPMAN
METHANE-Barrier 10/17/2023 Approved STUART CHAPMAN
METHANE-Subgrade 10/17/2023 Approved STUART CHAPMAN
Pre-Inspection 10/19/2023 Partial Approval CALEB MEISTER
Underground Mechanical 10/30/2023 Partial Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 11/1/2023 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 11/6/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 11/17/2023 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval RONNIE MINDANAO
HVAC-Rough 11/17/2023 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 11/17/2023 Partial Approval RONNIE MINDANAO
BUILDING-Rough-Frame 11/22/2023 Corrections Issued STUART CHAPMAN
HVAC-Rough 11/22/2023 Approved STUART CHAPMAN
Shower Pan 11/22/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/27/2023 Approved JUSTIN HAWLEY
HVAC-Rough 11/27/2023 Approved JUSTIN HAWLEY
Insulation 11/27/2023 Approved JUSTIN HAWLEY
METHANE-Rough 11/27/2023 Approved JUSTIN HAWLEY
PLUMBING-Rough 11/27/2023 Approved JUSTIN HAWLEY
Drywall Nailing 11/30/2023 Approved JUSTIN HAWLEY
Green Building Rough 11/30/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 11/30/2023 Partial Approval JUSTIN HAWLEY
Drywall Nailing 12/6/2023 Not Ready for Inspection LILIANA PORTILLO
Drywall Nailing 12/8/2023 Approved LILIANA PORTILLO
PLUMBING-Final 2/29/2024 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Rough 2/29/2024 Not Ready for Inspection JUSTIN HAWLEY
Special/Order Compliance 2/29/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 3/5/2024 Conditional Approval JUSTIN HAWLEY
Sewer 3/14/2024 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 3/19/2024 Conditional Approval JUSTIN HAWLEY
PLUMBING-Rough 4/2/2024 Not Ready for Inspection ENRIQUE MIRELES
Sewer 4/2/2024 Partial Approval ENRIQUE MIRELES
Gas Test 4/3/2024 Approved BRENDAN MORELLI
PLUMBING-Final 4/12/2024 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Not Ready JUSTIN HAWLEY
BUILDING-Rough-Frame 5/2/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Approved JUSTIN HAWLEY
Final 7/11/2024 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 7/11/2024 Approved JUSTIN HAWLEY
Green Building Final 7/11/2024 Approved JUSTIN HAWLEY
Smoke Detectors 7/11/2024 Approved JUSTIN HAWLEY
Final 7/18/2024 OK to Issue CofO JOAQUIN GREENOUGH