604 N ARDEN BLVD 90004
Certificate Information: 604 N ARDEN BLVD 90004
- Application / Permit
- 22016-10000-30258
- Plan Check / Job No.
- B22LA20007
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing detached garage into ADU per state law, all work per WFPP
- Permit Issued
- Issued on 8/29/2023
- Issuing Office
- Current Status
- CofO Issued on 1/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2022 | FERNANDO FLORES |
| Corrections Issued | 10/13/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 6/18/2023 | MINA HABILI |
| Plan Check Approved | 8/9/2023 | MINA HABILI |
| Issued | 8/29/2023 | APPLICANT |
| CofO in Progress | 12/12/2024 | JEFFREY MEAD |
| Permit Finaled | 1/12/2025 | DEROLD HAUFF |
| CofO Issued | 1/12/2025 | DEROLD HAUFF |
| Permit Finaled | 1/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/8/2023 | RIDWAN HARDY |
| Address approval | Cleared | 1/13/2023 | CINDY QI |
| Sewer availability | Cleared | 1/13/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2023 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/17/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 10/17/2023 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 10/17/2023 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 10/17/2023 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 10/17/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 10/25/2023 | Approved | JEFFREY MEAD |
| METHANE-Rough | 10/25/2023 | Approved | JEFFREY MEAD |
| Pre-Inspection | 10/25/2023 | Approved | JEFFREY MEAD |
| Sewer | 10/30/2023 | Approved | JEFFREY MEAD |
| Insulation | 11/22/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/5/2023 | Approved | JEFFREY MEAD |
| Shower Pan | 12/5/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Not Ready | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Not Ready | JEFFREY MEAD |
| Final | 3/1/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 3/1/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Not Required | JEFFREY MEAD |
| Smoke Detectors | 3/1/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 5/3/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 5/3/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Final | 5/3/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 5/3/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 10/17/2024 | Approved | JEFFREY MEAD |
| Final | 10/17/2024 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 10/17/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 10/17/2024 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 11/7/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 11/7/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 11/7/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 11/7/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/11/2024 | Approved | JEFFREY MEAD |
| Final | 12/11/2024 | OK to Issue CofO | JEFFREY MEAD |
| HVAC-Final | 12/11/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 12/11/2024 | Approved | JEFFREY MEAD |