1881 1/2 W 95TH ST 90047

Certificate Information: 1881 1/2 W 95TH ST 90047

Application / Permit
22016-10000-30140
Plan Check / Job No.
B22LA19926
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) 20' X 20' DETACHED 2-CAR GARAGE PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 12/20/2022
Issuing Office
Current Status
CofO Issued on 6/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2022 APPLICANT
Assigned to Plan Check Engineer 10/7/2022 GURUNATH NESARAJAH
Corrections Issued 10/8/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 12/7/2022 GURUNATH NESARAJAH
Plan Check Approved 12/16/2022 GURUNATH NESARAJAH
Issued 12/20/2022 APPLICANT
CofO in Progress 5/26/2023 ENRIQUE MIRELES
CofO in Progress 5/26/2023 ENRIQUE MIRELES
Permit Finaled 6/1/2023 DEROLD HAUFF
CofO Issued 6/1/2023 DEROLD HAUFF
Permit Finaled 6/1/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/15/2022 AMAAN MALIK
Sewer availability Cleared 10/15/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 10/18/2022 AMAAN MALIK
Construction near power lines Cleared 12/3/2022 RIDWAN HARDY
Construction within easement Cleared 12/3/2022 RIDWAN HARDY

Contact Information

Contractor Akr Construction Inc; Lic. No.: 1065837-B 12729 RIVERSIDE DR #301      VALLEY VILLAGE, CA 91607

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/31/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/7/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/9/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/27/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 2/27/2023 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 2/27/2023 Approved ENRIQUE MIRELES
HVAC-Rough 2/27/2023 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Rough 2/27/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/27/2023 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 3/3/2023 Approved ENRIQUE MIRELES
HVAC-Rough 3/3/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/3/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/9/2023 Approved ENRIQUE MIRELES
Insulation 3/9/2023 Approved ENRIQUE MIRELES
Drywall Nailing 3/14/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/14/2023 Approved ENRIQUE MIRELES
Shower Pan 3/14/2023 Approved ENRIQUE MIRELES
Final 4/18/2023 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 4/18/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/18/2023 Approved ENRIQUE MIRELES
Final 4/24/2023 Corrections Issued ENRIQUE MIRELES
Final 4/28/2023 Corrections Issued ENRIQUE MIRELES
Final 5/9/2023 OK to Issue CofO ENRIQUE MIRELES