860 S WOOSTER ST 100 90035
Certificate Information: 860 S WOOSTER ST 100 90035
- Application / Permit
- 22016-10000-30087
- Plan Check / Job No.
- B22LA19885
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERTING 359 S.F. STORAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 12/30/2022
- Issuing Office
- Current Status
- CofO Issued on 9/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2022 | SHANGQIN XIE |
| Corrections Issued | 10/19/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 12/27/2022 | SHANGQIN XIE |
| Plan Check Approved | 12/29/2022 | SHANGQIN XIE |
| Issued | 12/30/2022 | APPLICANT |
| CofO in Progress | 8/2/2024 | FARHAD DADBIN |
| CofO in Progress | 8/30/2024 | FARHAD DADBIN |
| Permit Finaled | 9/10/2024 | DAVID TSAU |
| CofO Issued | 9/10/2024 | DAVID TSAU |
| Permit Finaled | 9/10/2024 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 10/26/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2022 | STEVE MELGAR |
| "Q" conditions | Cleared | 12/5/2022 | DALIA MOKAYED |
| Tenant Habitability Plan | Cleared | 12/12/2022 | MICHAEL SOTO |
Contact Information
| Architect | Youssefzadeh,, Atabak; Lic. No.: C22727 | 438 S PECK DRIVE BEVERLY HILLS, CA 90212 |
| Contractor | Owner-Builder | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 2/22/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Final | 2/22/2023 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 2/22/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Final | 4/5/2023 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Not Ready | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | FARHAD DADBIN |
| Final | 7/26/2024 | OK to Issue CofO | FARHAD DADBIN |
| Smoke Detectors | 7/26/2024 | Approved | FARHAD DADBIN |