515 S FLOWER ST 28th Fl 90071

Certificate Information: 515 S FLOWER ST 28th Fl 90071

Application / Permit
22016-10000-30083
Plan Check / Job No.
B22LA19883
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
FULL FLOOR TENANT IMPROVEMENT ON 28TH FLOOR: MINOR INTERIOR DEMO, NEW NON-BEARING PARTITIONS, CEILING, MILWORK, AND FINISHES. (21,250 SF)
Permit Issued
Issued on 12/22/2022
Issuing Office
Current Status
Permit Finaled on 3/13/2024

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 LAWRENCE QUIRANTE
Corrections Issued 10/8/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 10/14/2022 APPLICANT
Plan Check Approved 11/7/2022 STANLEY RAAP
Issued 12/22/2022 APPLICANT
Permit Finaled 3/12/2024 LUIS CCAMACHO

Permit Application Clearance Information

Fire Marshal Fire Life Safety Cleared 10/25/2022 RONILO MULAWIN

Contact Information

Architect , Gensler; Lic. No.: C34719 500 S. FIGUEROA   LOS ANGELES    CALIFORNIA, CA 90071
Contractor Taslimi Construction Co Inc; Lic. No.: 475159-B 1805 COLORADO AVENUE      SANTA MONICA, CA 90404

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 2/9/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 2/22/2023 Partial Approval KATY RAMIREZ
Deputy Fireproofing 3/10/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 4/3/2023 Partial Inspection KATY RAMIREZ
Drywall Nailing 4/17/2023 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 4/17/2023 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 5/23/2023 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 5/30/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 6/8/2023 Partial Approval KATY RAMIREZ
T-Bar Ceiling 6/15/2023 Not Ready for Inspection KATY RAMIREZ
T-Bar Ceiling 6/27/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 7/21/2023 Partial Approval VAHE KELEDJIAN
Drywall Nailing 7/24/2023 Partial Approval VAHE KELEDJIAN
T-Bar Ceiling 9/1/2023 Partial Inspection VAHE KELEDJIAN
T-Bar Ceiling 9/18/2023 Partial Approval KATY RAMIREZ
Final 11/28/2023 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/28/2023 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 11/28/2023 Approved KATY RAMIREZ
Final 3/12/2024 Permit Finaled LUIS CCAMACHO