1415 1/2 S MEADOWBROOK AVE 90019
Certificate Information: 1415 1/2 S MEADOWBROOK AVE 90019
- Application / Permit
- 22016-10000-30080
- Plan Check / Job No.
- B22LA19881
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT PORTION OF EXISTING GARAGE (494 SF) THAT IS BELOW THE EXISITING DUPLEX TO AN ADU PER STATE LAW
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | KHUONG TRUONG |
| Corrections Issued | 10/9/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 11/15/2022 | APPLICANT |
| Plan Check Approved | 12/9/2022 | JOSEPH RAFOLS |
| Issued | 8/8/2023 | APPLICANT |
| CofO in Progress | 1/13/2026 | BRENDAN MORELLI |
| Permit Finaled | 1/13/2026 | DEROLD HAUFF |
| CofO Issued | 1/13/2026 | DEROLD HAUFF |
| Permit Finaled | 1/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/19/2022 | STEVE MELGAR |
| Address approval | Cleared | 10/20/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2022 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 12/6/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/13/2023 | Partial Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 9/15/2023 | Partial Approval | JOSE AVILA |
| Green Building Rough | 9/29/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 9/29/2023 | Corrections Issued | STUART CHAPMAN |
| Insulation | 10/11/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/11/2023 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 10/17/2023 | Corrections Issued | JOSH MEISTER |
| Pre-Inspection | 10/17/2023 | Approved | JOSH MEISTER |
| Footing/Foundation/Slab | 10/19/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 10/23/2023 | Approved | JOSE AVILA |
| Green Building Rough | 11/17/2023 | Approved | STUART CHAPMAN |
| Insulation | 11/17/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 11/17/2023 | Approved | STUART CHAPMAN |
| Final | 2/7/2024 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 2/7/2024 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 2/7/2024 | Approved | STUART CHAPMAN |
| Final | 1/13/2026 | OK to Issue CofO | BRENDAN MORELLI |