1901 W BRANDEN ST 1-7 90026

Certificate Information: 1901 W BRANDEN ST 1-7 90026

Application / Permit
22016-10000-29986
Plan Check / Job No.
B22LA19818
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Conversion of existing parking area to ADU in an existing apartment
Permit Issued
Issued on 3/30/2023
Issuing Office
Current Status
CofO Issued on 2/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 ARSALAN SHABESTARI
Corrections Issued 10/8/2022 ARSALAN SHABESTARI
Quality Review Completed 10/14/2022 FARUK SEZER
Plan Check Approved 2/7/2023 ARSALAN SHABESTARI
Issued 3/30/2023 APPLICANT
CofO in Progress 2/24/2026 RAFAEL CORTES
Permit Finaled 2/27/2026 ERNESTO CORRAL
CofO Issued 2/27/2026 ERNESTO CORRAL
Permit Finaled 2/27/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 10/19/2022 CINDY QI
Sewer availability Cleared 10/19/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/12/2023 CINDY QI
Grading Pre-Inspection Cleared 1/13/2023 KIRK LINKLATER
Green Code Cleared 1/31/2023 ARSALAN SHABESTARI

Contact Information

Contractor Jac Property Maintenance Services Inc; Lic. No.: 945315-B       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/7/2023 Approved TIMOTHY POWELL
Pre-Inspection 6/8/2023 Not Ready for Inspection TIMOTHY POWELL
Pre-Inspection 10/17/2023 Partial Inspection RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 2/20/2024 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 2/20/2024 Partial Approval RAMAZANALI ALMASI
Wall Anchors 2/20/2024 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 3/5/2024 Corrections Issued RAMAZANALI ALMASI
Green Building Rough 6/27/2024 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 6/27/2024 Not Ready for Inspection RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Approved RAMAZANALI ALMASI
Green Building Rough 7/22/2024 Not Ready for Inspection RAMAZANALI ALMASI
Interior/Exterior Lathing 8/7/2024 Approved RAMAZANALI ALMASI
Green Building Rough 5/2/2025 Approved LUIS CCAMACHO
Wall Anchors 5/2/2025 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 5/2/2025 Partial Approval LUIS CCAMACHO
Insulation 5/12/2025 Approved RONALD JIMENEZ
Drywall Nailing 5/23/2025 No Access for Inspection LARRY ARNICK
Drywall Nailing 5/27/2025 Approved RONALD JIMENEZ
Final 2/3/2026 Not Ready for Inspection RAFAEL CORTES
Green Building Final 2/3/2026 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Approved RAFAEL CORTES
Smoke Detectors 2/3/2026 Approved RAFAEL CORTES
Wood Frame 2/3/2026 Approved RAFAEL CORTES
Final 2/23/2026 Not Ready for Inspection SEAN POMISH
Final 2/24/2026 OK to Issue CofO RAFAEL CORTES