236 W 92ND ST 90003

Certificate Information: 236 W 92ND ST 90003

Application / Permit
22016-10000-29959
Plan Check / Job No.
B22LA19814
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING 360 SQ FT. DETACHED GARAGE INTO ADU WITH 184 SF ADDITION Per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 4/10/2023
Issuing Office
Current Status
CofO Issued on 1/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/7/2022 ZAW HAN
Corrections Issued 10/9/2022 ZAW HAN
Applicant returned to address corrections 3/22/2023 HANS SANTIAGO
Plan Check Approved 3/29/2023 ANDREW SANTIAGO
Issued 4/10/2023 APPLICANT
CofO in Progress 12/22/2023 MICHAEL LEWIS
CofO in Progress 12/22/2023 MICHAEL LEWIS
CofO in Progress 1/12/2024 MICHAEL LEWIS
Permit Finaled 1/13/2024 DEROLD HAUFF
Permit Finaled 1/13/2024 DEROLD HAUFF
CofO Issued 1/13/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/15/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 10/15/2022 JEANETTE VONG
Sewer availability Cleared 10/15/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/14/2023 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: C85148 422 FALLINGSTAR      IRVINE, CA 92614
Engineer Xi,, Wang; Lic. No.: NA85148       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/29/2023 Not Ready for Inspection MICHAEL LEWIS
Pre-Inspection 6/29/2023 Approved MICHAEL LEWIS
Deputy Drilled-In Anchors 8/8/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 8/9/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/9/2023 Partial Approval MICHAEL LEWIS
Underground Mechanical 8/9/2023 Not Ready for Inspection MICHAEL LEWIS
PLUMBING-Rough 8/11/2023 Approved MICHAEL LEWIS
Sewer 8/11/2023 Approved MICHAEL LEWIS
Underground Mechanical 8/11/2023 Approved MICHAEL LEWIS
Deputy Drilled-In Anchors 8/15/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Not Ready for Inspection MICHAEL LEWIS
Deputy Wood Construction 8/24/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 8/25/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Approved MICHAEL LEWIS
HVAC-Rough 8/25/2023 Corrections Issued MICHAEL LEWIS
MERV13>=Rough 8/25/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 8/25/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/6/2023 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 9/6/2023 Approved MICHAEL LEWIS
Underground Mechanical 9/6/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/11/2023 Partial Inspection MICHAEL LEWIS
HVAC-Rough 9/11/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/21/2023 Approved MICHAEL LEWIS
Insulation 9/21/2023 Approved MICHAEL LEWIS
Drywall Nailing 9/25/2023 Approved MICHAEL LEWIS
Shower Pan 9/28/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 12/18/2023 Corrections Issued MICHAEL LEWIS
Final 12/18/2023 Corrections Issued MICHAEL LEWIS
Gas Test 12/18/2023 Approved MICHAEL LEWIS
HVAC-Final 12/18/2023 Approved MICHAEL LEWIS
MERV13>=Final 12/18/2023 Approved MICHAEL LEWIS
PLUMBING-Final 12/18/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 12/18/2023 Corrections Issued MICHAEL LEWIS
Smoke Detectors 12/18/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 12/21/2023 Approved MICHAEL LEWIS
Final 12/21/2023 Corrections Issued MICHAEL LEWIS
Service/Power Release 12/21/2023 Approved MICHAEL LEWIS
Smoke Detectors 12/21/2023 Approved MICHAEL LEWIS
Final 12/22/2023 Corrections Issued MICHAEL LEWIS
Final 1/12/2024 OK to Issue CofO MICHAEL LEWIS