400 S HOPE ST 90071

Certificate Information: 400 S HOPE ST 90071

Application / Permit
22016-10000-29906
Plan Check / Job No.
B22LA19784
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EpLAN DEMOLITION OF EXISTING CONVENIENCE STAIR CONNECTING LEVELS 15 & 16, NEW RATED STRUCTURAL FLOOR INFILL AT STAIR OPENING BETWEEN LEVELS 15 & 16, AND PATCHING OF EXISTING FINISHES.
Permit Issued
Issued on 3/13/2023
Issuing Office
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 KAVIAN REFAHI
Corrections Issued 10/11/2022 KAVIAN REFAHI
Quality Review Completed 10/18/2022 CHIHARU SUZUKI
Applicant returned to address corrections 1/11/2023 KAVIAN REFAHI
Applicant returned to address corrections 2/23/2023 KAVIAN REFAHI
Plan Check Approved 3/9/2023 KAVIAN REFAHI
Issued 3/13/2023 APPLICANT
CofO in Progress 6/8/2023 KATY RAMIREZ
CofO Issued 6/8/2023 ERNESTO CORRAL
Permit Finaled 6/8/2023 ERNESTO CORRAL

Permit Application Clearance Information

Specific Plan Cleared 10/21/2022 MATHEW QUAN
Miscellaneous Cleared 10/24/2022 MAX LODER
Fire Marshal Fire Life Safety Cleared 10/30/2022 MENOA AGHAJANI
DAS Clearance Cleared 2/13/2023 Pranita Shah

Contact Information

Architect , ; Lic. No.: C34719 500 S FIGUEROA STREET      LOS ANGELES, CA 90071
Contractor Howard Building Corporation; Lic. No.: 445804-B       ,
Engineer Lam,, Howard K; Lic. No.: S2717 32712 RACHEL CIRCLE      DANA POINT, CA 92629

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 4/14/2023 Conditional Approval KATY RAMIREZ
Structural Steel Frame 4/17/2023 Partial Approval KATY RAMIREZ
Deputy Fireproofing 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 4/27/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 5/1/2023 Approved KATY RAMIREZ
Final 5/18/2023 Partial Inspection KATY RAMIREZ
Reinforced Concrete Frame 5/18/2023 Partial Approval KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 5/18/2023 Approved KATY RAMIREZ
Verify Sprinkler Sign Off 5/18/2023 Not Ready for Inspection KATY RAMIREZ
Final 6/9/2023 OK to Issue CofO KATY RAMIREZ
Reinforced Concrete Frame 6/9/2023 Approved KATY RAMIREZ
Verify Sprinkler Sign Off 6/9/2023 Approved KATY RAMIREZ