673 S SHATTO PL 1-40 90005
Certificate Information: 673 S SHATTO PL 1-40 90005
- Application / Permit
- 22016-10000-29834
- Plan Check / Job No.
- B22LA19714
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERSION OF (E) BASEMENT STORAGE ROOM INTO ONE ADU.
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- Issued on 1/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | JOE VO |
| Corrections Issued | 10/22/2022 | JOE VO |
| Quality Review Completed | 10/24/2022 | GARO TELMI |
| Plan Check Approved | 1/8/2024 | JOE VO |
| Issued | 1/18/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2022 | CINDY QI |
| Redevelopment Project Area | Cleared | 10/26/2022 | DAVID URITA |
| Sewer availability | Cleared | 10/26/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 12/5/2022 | KURT CORRAL |
| Fire Marshal Fire Life Safety | Cleared | 10/3/2023 | DOMINIQUE MEDINA |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: NA37588 | , |
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | , |
| Contractor | Aaron'S Pro Flooring; Lic. No.: 915352-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/16/2024 | Partial Inspection | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 3/29/2024 | Approved | JEROME BLACKWOOD |
| Wood Frame | 9/13/2024 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 9/27/2024 | Partial Approval | PAUL BAZERKANIAN |
| Insulation | 10/22/2024 | Corrections Issued | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 12/5/2024 | Approved | JEROME BLACKWOOD |