3218 1/4-1/2 N DIVISION ST 90065
Certificate Information: 3218 1/4-1/2 N DIVISION ST 90065
- Application / Permit
- 22016-10000-29827
- Plan Check / Job No.
- B22LA19707
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* CONVERT (E) ATTACHED 2-CAR GARAGE (445 SF) TO ADU PER CA GC 65852.2(e)(1)(A), EXISTING UNIT ABOVE TO REMAIN, NOT IN SCOPE.
- Permit Issued
- Issued on 12/21/2022
- Issuing Office
- Current Status
- CofO Issued on 1/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2022 | VIVIAN LAO |
| Corrections Issued | 10/6/2022 | VIVIAN LAO |
| Plan Check Approved | 12/13/2022 | VIVIAN LAO |
| Issued | 12/21/2022 | APPLICANT |
| CofO in Progress | 1/13/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled | 1/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | JEANIE LAM |
| Sewer availability | Cleared | 11/9/2022 | JEANIE LAM |
| Specific Plan | Cleared | 11/9/2022 | NASHYA JENSEN |
| Tenant Habitability Plan | Cleared | 11/10/2022 | ISMAEL HERNANDEZ |
| Grading Pre-Inspection | Cleared | 12/13/2022 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 12/13/2022 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ursu,, Dragos; Lic. No.: C79963 | 343 S MADISON AVE APT 19 PASADENA, CA 91101 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/16/2023 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 3/31/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 4/12/2023 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/20/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/12/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 5/12/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 5/12/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/16/2023 | Approved | OSVALDO PARAMO |
| Gas Test | 5/16/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 5/16/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 5/16/2023 | Approved | OSVALDO PARAMO |
| Insulation | 5/19/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 5/24/2023 | Approved | OSVALDO PARAMO |
| Sewer | 6/27/2023 | Approved | OSVALDO PARAMO |
| Final | 7/3/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 7/3/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 7/3/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 7/3/2023 | Approved | OSVALDO PARAMO |
| Final | 7/13/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 7/19/2023 | Corrections Issued | OSVALDO PARAMO |
| Final | 12/27/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 1/12/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 1/12/2024 | Approved | ALIZAH MAYAGOITIA |