3218 1/4-1/2 N DIVISION ST 90065

Certificate Information: 3218 1/4-1/2 N DIVISION ST 90065

Application / Permit
22016-10000-29827
Plan Check / Job No.
B22LA19707
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* CONVERT (E) ATTACHED 2-CAR GARAGE (445 SF) TO ADU PER CA GC 65852.2(e)(1)(A), EXISTING UNIT ABOVE TO REMAIN, NOT IN SCOPE.
Permit Issued
Issued on 12/21/2022
Issuing Office
Current Status
CofO Issued on 1/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/5/2022 VIVIAN LAO
Corrections Issued 10/6/2022 VIVIAN LAO
Plan Check Approved 12/13/2022 VIVIAN LAO
Issued 12/21/2022 APPLICANT
CofO in Progress 1/13/2024 ALIZAH MAYAGOITIA
CofO Issued 1/21/2024 DEROLD HAUFF
Permit Finaled 1/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/9/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/9/2022 JEANIE LAM
Sewer availability Cleared 11/9/2022 JEANIE LAM
Specific Plan Cleared 11/9/2022 NASHYA JENSEN
Tenant Habitability Plan Cleared 11/10/2022 ISMAEL HERNANDEZ
Grading Pre-Inspection Cleared 12/13/2022 KIRK LINKLATER
Hydrant and Access approval Cleared 12/13/2022 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Ursu,, Dragos; Lic. No.: C79963 343 S MADISON AVE APT 19      PASADENA, CA 91101

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/16/2023 Approved ALIZAH MAYAGOITIA
Pre-Inspection 3/31/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 4/12/2023 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/20/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/12/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Approved OSVALDO PARAMO
HVAC-Rough 5/12/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 5/12/2023 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 5/16/2023 Approved OSVALDO PARAMO
Gas Test 5/16/2023 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 5/16/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 5/16/2023 Approved OSVALDO PARAMO
Insulation 5/19/2023 Approved OSVALDO PARAMO
Drywall Nailing 5/24/2023 Approved OSVALDO PARAMO
Sewer 6/27/2023 Approved OSVALDO PARAMO
Final 7/3/2023 Corrections Issued OSVALDO PARAMO
Green Building Final 7/3/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/3/2023 SGSOV Approved OSVALDO PARAMO
Service/Power Release 7/3/2023 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 7/3/2023 Approved OSVALDO PARAMO
Final 7/13/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 7/19/2023 Corrections Issued OSVALDO PARAMO
Final 12/27/2023 Not Ready for Inspection JEFFREY MEAD
Final 1/12/2024 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 1/12/2024 Approved ALIZAH MAYAGOITIA