5540 W SPOKANE ST 90016
Certificate Information: 5540 W SPOKANE ST 90016
- Application / Permit
- 22016-10000-29821
- Plan Check / Job No.
- B22LA19705
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITION TO (E) SFD.
- Permit Issued
- Issued on 12/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | ADRIANA LOPEZ |
| Corrections Issued | 11/10/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 11/23/2022 | KEN GILL |
| Building Plans Picked Up | 11/29/2022 | APPLICANT |
| Plan Check Approved | 12/21/2022 | ADRIANA LOPEZ |
| Issued | 12/28/2022 | APPLICANT |
| CofO in Progress | 11/16/2023 | JOSE AVILA |
| CofO Issued | 11/29/2023 | DEROLD HAUFF |
| Permit Finaled | 11/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/6/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 1/10/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 1/12/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 2/1/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 2/7/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/7/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/14/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 2/27/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 2/27/2023 | Approved | JOSE AVILA |
| Deputy Wood Construction | 3/1/2023 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | JOSE AVILA |
| Green Building Rough | 3/6/2023 | Approved | JOSE AVILA |
| Insulation | 3/6/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 3/6/2023 | Partial Approval | JOSE AVILA |
| Drywall Nailing | 3/17/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 3/17/2023 | Approved | MICHAEL LEWIS |
| Final | 6/6/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 6/6/2023 | Approved | JOSE AVILA |
| Green Building Final | 6/6/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 6/6/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 8/31/2023 | Approved | JOSE AVILA |
| Final | 8/31/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 8/31/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 8/31/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 8/31/2023 | Approved | JOSE AVILA |
| Final | 11/16/2023 | OK to Issue CofO | JOSE AVILA |