555 S MATEO ST Building 3 90013

Certificate Information: 555 S MATEO ST Building 3 90013

Application / Permit
22016-10000-29769
Plan Check / Job No.
B22LA19664
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EPLAN First Tenant Improvement for Core & Shell. Change of Use from Retail to Office at a portion of an existing 1-story Commercial Building
Permit Issued
Issued on 2/22/2023
Issuing Office
Current Status
Issued on 2/22/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/30/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 PRANITA SHAH
Corrections Issued 10/13/2022 PRANITA SHAH
Quality Review Completed 11/8/2022 JOHN FRANCIA
Applicant returned to address corrections 1/12/2023 PRANITA SHAH
Plan Check Approved 2/15/2023 PRANITA SHAH
Issued 2/22/2023 APPLICANT

Permit Application Clearance Information

Green Code Cleared 1/9/2023 MICHAEL PEREZ
DAS Clearance Cleared 1/11/2023 MICHAEL PEREZ

Contact Information

Architect Thompson,, Colin Mckay; Lic. No.: NA33863       ,
Contractor Howard Building Corporation; Lic. No.: 445804-B       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 3/20/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Methane Barrier 4/4/2023 Conditional Approval JULIAN CAPUCETTI
Light Gage Steel Frame 4/10/2023 Approved JULIAN CAPUCETTI
Structural Steel Frame 4/10/2023 Approved JULIAN CAPUCETTI
Drywall Nailing 4/12/2023 Partial Approval JULIAN CAPUCETTI
Insulation 4/12/2023 Approved JULIAN CAPUCETTI
Drywall Nailing 4/17/2023 Partial Approval JULIAN CAPUCETTI
Deputy Methane Barrier 4/18/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Drilled-In Anchors 4/21/2023 Conditional Approval JULIAN CAPUCETTI
Excavation/Setback/Form/Re-Bar 4/21/2023 Approved JULIAN CAPUCETTI
METHANE-Final 4/21/2023 Approved JULIAN CAPUCETTI
Light Gage Steel Frame 5/25/2023 Partial Approval JULIAN CAPUCETTI
Drywall Nailing 5/30/2023 Approved JULIAN CAPUCETTI
Drywall Nailing 6/5/2023 Approved JULIAN CAPUCETTI
T-Bar Ceiling 6/5/2023 Approved JULIAN CAPUCETTI
Final 6/14/2023 Not Ready for Inspection JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Not Ready JULIAN CAPUCETTI
Smoke Detectors 6/14/2023 Not Ready for Inspection JULIAN CAPUCETTI
Wood Frame 6/14/2023 Approved JULIAN CAPUCETTI
Final 6/16/2023 Not Ready for Inspection JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Not Ready JULIAN CAPUCETTI
Smoke Detectors 6/16/2023 Not Ready for Inspection JULIAN CAPUCETTI
Final 6/23/2023 Conditional Approval ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 6/23/2023 Approved ALFREDO LOPEZ
Final 6/26/2023 Partial Approval JULIAN CAPUCETTI
Final 4/3/2024 Corrections Issued RONALD JIMENEZ