1307 N SUNSET PLAZA DR 90069
Certificate Information: 1307 N SUNSET PLAZA DR 90069
- Application / Permit
- 22016-10000-29764
- Plan Check / Job No.
- B22LA19658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached Garage to ADU CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- Metro
- Current Status
- Issued on 1/31/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2022 | DANIEL SMILEY |
| Corrections Issued | 10/5/2022 | DANIEL SMILEY |
| Building Plans Picked Up | 10/12/2022 | APPLICANT |
| Plan Check Approved | 1/13/2023 | KHUONG TRUONG |
| Issued | 1/31/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2023 | JEANIE LAM |
| Sewer availability | Cleared | 1/12/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2023 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 1/13/2023 | KIRK LINKLATER |
Contact Information
| Contractor | Kenneth Cronon Inc; Lic. No.: 1029229-B | 10413 HAINES CYN AVE TUJUNGA, CA 91042 |
| Engineer | Samara,, Muzahim; Lic. No.: C26015 | 9100 S SEPULVEDA BLVD SUITE 115 LOS ANGELES, CA 90045 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/1/2023 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 2/1/2023 | Partial Inspection | RAUL BARAJAS |
| Underground Mechanical | 2/1/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/6/2023 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/15/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/24/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/22/2023 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/22/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/22/2023 | Approved | RAUL BARAJAS |
| Green Building Rough | 5/22/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 5/22/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Test | 6/16/2023 | Approved | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 6/16/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/1/2023 | Approved | RAUL BARAJAS |