5417 S HILLCREST DR 90043
Certificate Information: 5417 S HILLCREST DR 90043
- Application / Permit
- 22016-10000-29686
- Plan Check / Job No.
- B22LA19587
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert existing (800sf) Detached Recreation Room with 1-car Carport to Accessory Dwelling Unit with 1-car Carport per CA Govt. Code 65852.2(e)(1)(A). COMPLY WITH DEPARTMENT ORDER effective date 06/08/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- CofO Issued on 10/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2022 | PRANITA SHAH |
| Corrections Issued | 10/6/2022 | PRANITA SHAH |
| Plan Check Approved | 2/15/2023 | KEVIN MORALES |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 10/23/2023 | JOHN PARKER |
| Permit Finaled | 10/27/2023 | BRUCE TODD |
| CofO Issued | 10/27/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 1/26/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Final | 3/17/2023 | Not Ready for Inspection | ENRIQUE PREZA |
| PLUMBING-Final | 3/17/2023 | Not Ready for Inspection | ENRIQUE PREZA |
| Pre-Inspection | 3/17/2023 | Corrections Issued | ENRIQUE PREZA |
| Gas Test | 4/26/2023 | Corrections Issued | ENRIQUE PREZA |
| Gas Test | 5/2/2023 | Partial Approval | ENRIQUE PREZA |
| ELECTRICAL-Final | 7/7/2023 | Corrections Issued | ENRIQUE PREZA |
| Gas Test | 7/7/2023 | Corrections Issued | ENRIQUE PREZA |
| Grounding or Bonding | 7/7/2023 | Approved | ENRIQUE PREZA |
| Wood Frame | 7/7/2023 | Approved | ENRIQUE PREZA |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | JOHN PARKER |
| ELECTRICAL-Final | 10/6/2023 | Approved | JOHN PARKER |
| Final | 10/6/2023 | Conditional Approval | JOHN PARKER |
| Gas Test | 10/6/2023 | Approved | JOHN PARKER |
| HVAC-Final | 10/6/2023 | Approved | JOHN PARKER |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Approved | JOHN PARKER |
| Service/Power Release | 10/6/2023 | Approved | JOHN PARKER |
| Smoke Detectors | 10/6/2023 | Approved | JOHN PARKER |