159 N CATALINA ST 90004
Certificate Information: 159 N CATALINA ST 90004
- Application / Permit
- 22016-10000-29479
- Plan Check / Job No.
- B22LA19473
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED 2CAR GARAGE 483SF TO ACCESSORY DWELLING UNIT Per State Law and GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 3/29/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | ZAW HAN |
| Corrections Issued | 10/6/2022 | ZAW HAN |
| Building Plans Picked Up | 10/11/2022 | APPLICANT |
| Plan Check Approved | 3/29/2023 | JOSEPH RAFOLS |
| Issued | 3/29/2023 | APPLICANT |
| CofO in Progress | 10/15/2024 | WILLIAM MICHALAK |
| Permit Finaled | 11/12/2025 | CLAUDIO MORENO |
| CofO Issued | 11/12/2025 | CLAUDIO MORENO |
| Permit Finaled | 11/12/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Hold | Cleared | 11/7/2022 | MARIA VENDIVIL |
| Address approval | Cleared | 11/9/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 11/9/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 11/9/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | AMAAN MALIK |
| Specific Plan | Cleared | 2/17/2023 | DANALYNN DOMINGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Orellana,, Fredy Orlando; Lic. No.: C68955 | 100 SPECTRUM CENTER DR STE 9-283 IRVINE, CA 92618 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/21/2023 | Approved | WILLIAM MICHALAK |
| Pre-Inspection | 3/12/2024 | Partial Approval | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 3/20/2024 | Corrections Issued | WILLIAM MICHALAK |
| PLUMBING-Rough | 3/20/2024 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 3/27/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| PLUMBING-Rough | 3/27/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 4/2/2024 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 4/2/2024 | Corrections Issued | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Partial Approval | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 4/4/2024 | Partial Approval | WILLIAM MICHALAK |
| Insulation | 4/29/2024 | Partial Approval | WILLIAM MICHALAK |
| Drywall Nailing | 5/13/2024 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 5/13/2024 | Approved | WILLIAM MICHALAK |
| Final | 6/11/2024 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Final | 6/11/2024 | Corrections Issued | WILLIAM MICHALAK |
| METHANE-Final | 6/11/2024 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 6/11/2024 | Approved | WILLIAM MICHALAK |
| Final | 8/14/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Final | 8/15/2024 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 8/15/2024 | SGSOV Approved | WILLIAM MICHALAK |
| Final | 10/15/2024 | OK to Issue CofO | WILLIAM MICHALAK |