4441 W KINGSWELL AVE 90027
Certificate Information: 4441 W KINGSWELL AVE 90027
- Application / Permit
- 22016-10000-29471
- Plan Check / Job No.
- B22LA19467
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING DETACHED 19'4" X 19'6" GARAGE TO ADU per state law work done per wfpp
- Permit Issued
- Issued on 12/9/2022
- Issuing Office
- Current Status
- CofO Issued on 7/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2022 | JOSEPH RAFOLS |
| Corrections Issued | 10/5/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 12/7/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 12/8/2022 | KHUONG TRUONG |
| Issued | 12/9/2022 | APPLICANT |
| CofO in Progress | 6/30/2023 | JOSEPH MCGARRY |
| Permit Finaled | 7/13/2023 | DEROLD HAUFF |
| CofO Issued | 7/13/2023 | DEROLD HAUFF |
| Permit Finaled | 7/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/18/2022 | KIRK LINKLATER |
| Address approval | Cleared | 10/25/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | JEANIE LAM |
| Sewer availability | Cleared | 10/25/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 12/3/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Livingprospex Corporation; Lic. No.: 1064984-B | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2022 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/27/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/3/2023 | Approved | JOSEPH MCGARRY |
| Sewer | 1/3/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Sewer | 1/18/2023 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 1/18/2023 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/16/2023 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 2/16/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 2/16/2023 | Partial Inspection | RAUL BARAJAS |
| Wood Frame | 2/16/2023 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/22/2023 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/22/2023 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 2/22/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 2/22/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/22/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 3/8/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/8/2023 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 3/28/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/28/2023 | Approved | JOSEPH MCGARRY |
| Shower Pan | 3/28/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/13/2023 | Approved | JOSEPH MCGARRY |
| Final | 6/13/2023 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 6/13/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 6/13/2023 | Approved | JOSEPH MCGARRY |
| Final | 6/28/2023 | OK to Issue CofO | JOSEPH MCGARRY |