2001-2003 N ALVARADO ST 90039

Certificate Information: 2001-2003 N ALVARADO ST 90039

Application / Permit
22016-10000-29143
Plan Check / Job No.
B22LA19286
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
COVNERT PORTION OF (E) DUPLEX (2440 SQ FT) IN TO A (N) ADU (432 SQ FT) *ADU ADDRESS IS 2001 1/2 N ALVARADO ST *
Permit Issued
Issued on 9/28/2022
Issuing Office
Current Status
CofO Issued on 3/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2022 APPLICANT
Assigned to Plan Check Engineer 9/23/2022 FERNANDO FLORES
Corrections Issued 9/23/2022 FERNANDO FLORES
Plan Check Approved 9/28/2022 JOSEPH RAFOLS
Issued 9/28/2022 APPLICANT
CofO in Progress 3/2/2023 THOMAS LOGRASSO
Permit Finaled 3/6/2023 DEROLD HAUFF
CofO Issued 3/6/2023 DEROLD HAUFF
Permit Finaled 3/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/24/2022 JEANETTE VONG
Sewer availability Cleared 9/24/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/27/2022 JEANETTE VONG
Tenant Habitability Plan Cleared 9/28/2022 JUAN ACOSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/20/2022 Partial Inspection THOMAS LOGRASSO
Wood Frame 12/15/2022 Partial Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 12/23/2022 Partial Approval THOMAS LOGRASSO
Insulation 12/23/2022 Partial Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 12/23/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 12/30/2022 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 12/30/2022 Partial Approval THOMAS LOGRASSO
HVAC-Rough 12/30/2022 Conditional Approval THOMAS LOGRASSO
Insulation 12/30/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 12/30/2022 Partial Approval THOMAS LOGRASSO
Insulation 1/4/2023 Conditional Approval THOMAS LOGRASSO
Drywall Nailing 1/6/2023 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 1/20/2023 Approved THOMAS LOGRASSO
Drywall Nailing 1/20/2023 Approved THOMAS LOGRASSO
MERV13>=Rough 1/20/2023 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 1/20/2023 Approved THOMAS LOGRASSO
Final 2/23/2023 Corrections Issued STUART CHAPMAN
MERV13>=Final 2/23/2023 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 2/23/2023 Approved STUART CHAPMAN
Final 3/1/2023 OK to Issue CofO THOMAS LOGRASSO