17636 W DELANO ST 91316
Certificate Information: 17636 W DELANO ST 91316
- Application / Permit
- 22016-10000-29134
- Plan Check / Job No.
- B22LA19276
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: MAJOR INTERIOR REMODEL & 18'-7.75" X 28'-5" ADDITION TO REAR OF SINGLE FAMILY DWELLING - ALL WORK PER ENGINEER
- Permit Issued
- Issued on 2/17/2023
- Issuing Office
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/27/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 11/30/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 12/22/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/17/2023 | ALEC MOUSAKHANIAN |
| Issued | 2/17/2023 | APPLICANT |
| CofO in Progress | 6/5/2024 | JON MCHUGH |
| Permit Finaled | 7/9/2024 | JOHN JANSON |
| CofO Issued | 7/9/2024 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/18/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 2/7/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/9/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 2/9/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: NA50989 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/16/2023 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/15/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 7/13/2023 | Corrections Issued | JON MCHUGH |
| Sewer | 7/19/2023 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 7/19/2023 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Corrections Issued | JON MCHUGH |
| Deputy Wood Construction | 9/27/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/17/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 10/17/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 10/17/2023 | Corrections Issued | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 10/17/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 10/23/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 10/23/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 10/23/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | JON MCHUGH |
| Green Building Rough | 10/25/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/25/2023 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 10/25/2023 | Approved | JON MCHUGH |
| Insulation | 10/30/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 11/3/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/17/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Shower Pan | 11/17/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/22/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 12/19/2023 | Approved | JEFFREY PARD |
| Gas Test | 12/19/2023 | Approved | JEFFREY PARD |
| HVAC-Final | 1/5/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 1/5/2024 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 1/12/2024 | Approved | JON MCHUGH |
| Final | 1/12/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 1/12/2024 | Approved | JON MCHUGH |
| HVAC-Final | 1/12/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 1/12/2024 | Approved | JON MCHUGH |
| Final | 6/5/2024 | OK to Issue CofO | JON MCHUGH |
| Footing/Foundation/Slab | 6/5/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 6/5/2024 | Approved | JON MCHUGH |