3613 S HILLCREST DR 90016

Certificate Information: 3613 S HILLCREST DR 90016

Application / Permit
22016-10000-29024
Plan Check / Job No.
B22LA19204
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 18' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2 (e) (1) (A). ALL WORK PER WFPP.
Permit Issued
Issued on 10/13/2022
Issuing Office
Current Status
CofO Issued on 5/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2022 APPLICANT
Assigned to Plan Check Engineer 9/26/2022 ALEC MOUSAKHANIAN
Corrections Issued 9/27/2022 ALEC MOUSAKHANIAN
Plan Check Approved 10/11/2022 ALEC MOUSAKHANIAN
Issued 10/13/2022 APPLICANT
CofO in Progress 5/2/2023 ANTHONY EGSON
Permit Finaled 5/13/2023 DEROLD HAUFF
CofO Issued 5/13/2023 DEROLD HAUFF
Permit Finaled 5/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 9/28/2022 WALTER RAMIREZ
Address approval Cleared 9/30/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/30/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 9/30/2022 CELINA MORENO
Sewer availability Cleared 9/30/2022 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/10/2022 Corrections Issued ANTHONY EGSON
Rough-Elec/Plmb/HVAC 11/10/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 11/29/2022 Corrections Issued ANTHONY EGSON
Underground Mechanical 11/29/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 12/5/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 12/5/2022 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 12/5/2022 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 1/13/2023 Partial Approval ANTHONY EGSON
PLUMBING-Rough 1/13/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 1/18/2023 Approved ANTHONY EGSON
PLUMBING-Rough 1/18/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 2/6/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 2/6/2023 Approved STUART CHAPMAN
HVAC-Rough 2/6/2023 Approved STUART CHAPMAN
Insulation 2/9/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/9/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval ANTHONY EGSON
Drywall Nailing 3/6/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/6/2023 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 3/10/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 3/31/2023 Approved ANTHONY EGSON
Final 3/31/2023 Corrections Issued ANTHONY EGSON
Green Building Final 3/31/2023 Approved ANTHONY EGSON
Green Building Rough 3/31/2023 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 3/31/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 4/12/2023 Approved ANTHONY EGSON
Final 4/12/2023 Corrections Issued ANTHONY EGSON
HVAC-Final 4/12/2023 Approved ANTHONY EGSON
PLUMBING-Final 4/12/2023 Approved ANTHONY EGSON
Service/Power Release 4/12/2023 Approved ANTHONY EGSON
Final 4/18/2023 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Approved ANTHONY EGSON
Final 4/25/2023 Not Ready for Inspection ANTHONY EGSON
Final 5/1/2023 OK to Issue CofO ANTHONY EGSON
Service/Power Release 5/2/2023 Approved ANTHONY EGSON