3348 E LOOSMORE ST 90065
Certificate Information: 3348 E LOOSMORE ST 90065
- Application / Permit
- 22016-10000-28877
- Plan Check / Job No.
- B22LA19082
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 18' 1" X 18' 2" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 10/1/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/22/2022 | GURUNATH NESARAJAH |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 5/13/2024 | OSVALDO PARAMO |
| Permit Finaled | 5/15/2024 | DEROLD HAUFF |
| CofO Issued | 5/15/2024 | DEROLD HAUFF |
| Permit Finaled | 5/15/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/14/2022 | KIRK LINKLATER |
| Address approval | Cleared | 11/16/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 11/16/2022 | TREVOR QUAN |
| Construction near power lines | Cleared | 12/17/2022 | RIDWAN HARDY |
| Supp. Use District POD/CDO/TDO | Cleared | 12/19/2022 | NASHYA JENSEN |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/3/2023 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 2/6/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Approved | OSVALDO PARAMO |
| Special/Order Compliance | 2/24/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/8/2023 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/8/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2023 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 6/8/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 6/8/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 6/27/2023 | Approved | OSVALDO PARAMO |
| Shower Pan | 6/27/2023 | Approved | OSVALDO PARAMO |
| Deputy Wood Construction | 11/7/2023 | Conditional Approval | OSVALDO PARAMO |
| Insulation | 11/30/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/30/2023 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 12/6/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/11/2023 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 1/16/2024 | Partial Approval | OSVALDO PARAMO |
| Gas Test | 3/5/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Gas Test | 3/6/2024 | Approved | OSVALDO PARAMO |
| Final | 3/11/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 3/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 3/11/2024 | Approved | OSVALDO PARAMO |
| Final | 3/14/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 3/14/2024 | Approved | OSVALDO PARAMO |
| Final | 4/29/2024 | OK to Issue CofO | OSVALDO PARAMO |