705 S LINCOLN BLVD 90291

Certificate Information: 705 S LINCOLN BLVD 90291

Application / Permit
22016-10000-28732
Plan Check / Job No.
B22LA18947
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Tenant improvement to (E) retail space to connect into adjacent restaurant. New openings between 2 tenants (Dining area not expanded)
Permit Issued
Issued on 9/22/2023
Issuing Office
Current Status
Permit Finaled on 11/30/2023

Permit Application Status History

Submitted 9/22/2022 APPLICANT
Assigned to Plan Check Engineer 9/27/2022 PRANITA SHAH
Corrections Issued 9/28/2022 PRANITA SHAH
Applicant returned to address corrections 4/20/2023 HERNAN ARREOLA
Applicant returned to address corrections 4/27/2023 HERNAN ARREOLA
Applicant returned to address corrections 5/4/2023 HERNAN ARREOLA
Applicant returned to address corrections 5/9/2023 HERNAN ARREOLA
Applicant returned to address corrections 6/5/2023 HERNAN ARREOLA
Plan Check Approved 8/31/2023 HERNAN ARREOLA
Issued 9/22/2023 APPLICANT
Permit Finaled 11/30/2023 FARHAD DADBIN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/13/2023 SAUL GARCIA
Sewer availability Cleared 2/13/2023 SAUL GARCIA
Comm Cor/Mini-Mall Cleared 5/18/2023 DALIA MOKAYED
Comm Cor/Mini-Mall Cleared 5/18/2023 DALIA MOKAYED
ZA Case Cleared 5/22/2023 MATTHEW COMPANA
ZA Case Cleared 5/22/2023 MATTHEW COMPANA
Food establishment approval Cleared 6/22/2023 LACDHS APPROVED
"Q" conditions Cleared 7/25/2023 JACKSON OLSON
Supp. Use District POD/CDO/TDO Cleared 7/25/2023 JACKSON OLSON
Coastal Zone Cleared 8/7/2023 LOUIS ORTEGA
Comm Cor/Mini-Mall Cleared 8/7/2023 LOUIS ORTEGA
Specific Plan Cleared 8/22/2023 JACKSON OLSON
Specific Plan Cleared 8/23/2023 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 10/13/2023 Not Ready for Inspection AMANUEL BERHE
Light Gage Steel Frame 10/13/2023 Approved AMANUEL BERHE
Drywall Nailing 10/17/2023 Approved AMANUEL BERHE
Final 10/30/2023 Corrections Issued CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 10/30/2023 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 10/30/2023 Not Ready for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Not Ready CASIMIR BRITTON
Final 11/29/2023 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 11/29/2023 Not Ready for Inspection FARHAD DADBIN
Final 11/30/2023 Permit Finaled FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV No Gas FARHAD DADBIN