2930 S RIDGELEY DR 90016
Certificate Information: 2930 S RIDGELEY DR 90016
- Application / Permit
- 22016-10000-28464
- Plan Check / Job No.
- B22LA18785
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install 1 SCCS, Check Relative Strength on North Elevation by alternative method per ordinance.
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Current Status
- CofC Issued on 7/6/2023
Permit Application Status History
| Submitted | 9/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | BIDYUT RATH |
| Corrections Issued | 9/29/2022 | BIDYUT RATH |
| Quality Review Completed | 9/30/2022 | HANS SANTIAGO |
| Plan Check Approved | 10/12/2022 | BIDYUT RATH |
| Issued | 10/27/2022 | APPLICANT |
| OK for CofC | 2/6/2023 | DARRYL ARNOLD |
| Permit Finaled | 4/7/2023 | DARRYL ARNOLD |
| CofC Issued | 7/6/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/27/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/1/2022 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 11/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 11/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 11/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 11/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/23/2022 | Approved | DARRYL ARNOLD |
| Final | 2/6/2023 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/6/2023 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 2/6/2023 | Approved | DARRYL ARNOLD |
| Final | 4/7/2023 | Permit Finaled | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/7/2023 | Approved | DARRYL ARNOLD |