133 S VISTA ST 90036
Certificate Information: 133 S VISTA ST 90036
- Application / Permit
- 22016-10000-28385
- Plan Check / Job No.
- B22LA18740
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Convert detached garage to ADU per state law. New windows and doors.
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Current Status
- CofO Issued on 9/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2022 | RICARDO RAMIREZ |
| Corrections Issued | 10/14/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 11/20/2022 | KEVIN MORALES |
| Issued | 11/21/2022 | APPLICANT |
| Permit Finaled | 9/7/2024 | RUBEN SALAS |
| CofO Issued | 9/7/2024 | RUBEN SALAS |
| Permit Finaled | 9/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2022 | CELINA MORENO |
| Sewer availability | Cleared | 10/20/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2022 | CELINA MORENO |
| HPOZ | Cleared | 11/3/2022 | DAMIAN GATTO |
| Miscellaneous | Cleared | 11/3/2022 | DAMIAN GATTO |
| ZI | Cleared | 11/3/2022 | DAMIAN GATTO |
Contact Information
| Architect | Rabin,, Daniel H; Lic. No.: C36893 | 1655 N BENTON WAY LOS ANGELES, CA 90026 |
| Architect | Rabin,, Daniel H; Lic. No.: NA36893 | , |
| Contractor | Luis Chavez Construction Inc; Lic. No.: 1024942-B | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/29/2022 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 12/20/2022 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 12/20/2022 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/23/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2023 | No Access for Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/8/2023 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 8/8/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 8/10/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 8/10/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/12/2023 | Approved | RICHARD ROBLES |
| ELECTRICAL-Rough | 8/12/2023 | Conditional Approval | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2023 | Approved | RICHARD ROBLES |
| HVAC-Rough | 8/12/2023 | Conditional Approval | RICHARD ROBLES |
| METHANE-Rough | 8/12/2023 | Approved | RICHARD ROBLES |
| HVAC-Rough | 8/18/2023 | Approved | LILIANA PORTILLO |
| Insulation | 8/18/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/18/2023 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 8/24/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 4/25/2024 | No Access for Inspection | AMIR NAZARIAN |
| Interior/Exterior Lathing | 4/26/2024 | Partial Approval | AMIR NAZARIAN |
| Shower Pan | 4/26/2024 | Approved | AMIR NAZARIAN |
| Final | 8/14/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2024 | SGSOV Approved | AMIR NAZARIAN |
| Smoke Detectors | 8/14/2024 | Approved | AMIR NAZARIAN |
| Special/Order Compliance | 8/14/2024 | Approved | LUIS CASTRO |
| Final | 8/26/2024 | Conditional Approval | JEFFREY MEAD |