4429 S PURDUE AVE 90230
Certificate Information: 4429 S PURDUE AVE 90230
- Application / Permit
- 22016-10000-28064
- Plan Check / Job No.
- B22LA18655
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 20' 4" X 20' 4" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 12/21/2022
- Issuing Office
- Current Status
- CofO Issued on 4/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 9/22/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/2/2022 | GURUNATH NESARAJAH |
| Issued | 12/21/2022 | APPLICANT |
| CofO in Progress | 4/16/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 4/20/2023 | DANIEL ORRANTE |
| CofO Issued | 4/20/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/20/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/11/2022 | JENSON LEE |
| Address approval | Cleared | 10/12/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | JENSON LEE |
| Construction near power lines | Cleared | 11/30/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Oro Coast Builders Inc; Lic. No.: 1063640-B | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/11/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/18/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 1/18/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/18/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/18/2023 | Approved | JESUS RODRIGUEZ |
| Sewer | 1/18/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 1/24/2023 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 1/24/2023 | Approved | HERBERT GIRON |
| Shower Pan | 1/24/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 1/26/2023 | Approved | HERBERT GIRON |
| Insulation | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/31/2023 | Partial Approval | HERBERT GIRON |
| Insulation | 1/31/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 2/28/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 2/28/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Not Ready | HERBERT GIRON |
| ELECTRICAL-Final | 4/10/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 4/10/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 4/10/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/14/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/14/2023 | Approved | JESUS RODRIGUEZ |
| Final | 4/14/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 4/14/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 4/14/2023 | Approved | JESUS RODRIGUEZ |
| MERV13>=Final | 4/14/2023 | Approved | JESUS RODRIGUEZ |
| MERV13>=Rough | 4/14/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/14/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/14/2023 | Approved | JESUS RODRIGUEZ |