6335 W 83RD ST 90045

Certificate Information: 6335 W 83RD ST 90045

Application / Permit
22016-10000-27934
Plan Check / Job No.
B22LA18570
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN 1. CONVERSION OF AN EXISTING 195 SQ.FT. RECROOM INTO AN ACCESSORY DWELLING UNIT + ADDITION PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/3/2023
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 DANIEL SANJUAN
Corrections Issued 9/30/2022 DANIEL SANJUAN
Applicant returned to address corrections 11/17/2022 DANIEL SANJUAN
Plan Check Approved 12/8/2022 RAHEL BEYENE
Issued 1/3/2023 APPLICANT
CofO in Progress 5/5/2023 HERBERT GIRON
Permit Finaled 5/11/2023 DANIEL ORRANTE
CofO Issued 5/11/2023 DANIEL ORRANTE
Permit Finaled 5/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 10/13/2022 ROBERT SANCHEZ
Address approval Cleared 10/14/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/17/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 10/17/2022 DINAH GARIN
Sewer availability Cleared 10/17/2022 DINAH GARIN
Construction near power lines Cleared 12/7/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/6/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 2/13/2023 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 2/16/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 2/16/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 3/16/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 3/16/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 3/16/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 3/20/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 3/20/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/23/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Approved BOBBY KEY
HVAC-Rough 3/23/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 3/30/2023 Approved HERBERT GIRON
Green Building Rough 3/30/2023 Approved HERBERT GIRON
Insulation 3/30/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 3/30/2023 Partial Approval HERBERT GIRON
Drywall Nailing 3/31/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 4/5/2023 Approved BOBBY KEY
Shower Pan 4/5/2023 Approved BOBBY KEY
ELECTRICAL-Final 4/20/2023 Corrections Issued HERBERT GIRON
Final 4/20/2023 Corrections Issued HERBERT GIRON
HVAC-Final 4/20/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 4/20/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 4/20/2023 Approved HERBERT GIRON
ELECTRICAL-Final 5/2/2023 Approved HERBERT GIRON
Final 5/2/2023 Corrections Issued HERBERT GIRON
Green Building Final 5/2/2023 Approved HERBERT GIRON
HVAC-Final 5/2/2023 Approved HERBERT GIRON
PLUMBING-Final 5/2/2023 Approved HERBERT GIRON
Final 5/5/2023 OK to Issue CofO HERBERT GIRON