11801 W VENTURA BLVD 91604
Certificate Information: 11801 W VENTURA BLVD 91604
- Application / Permit
- 22016-10000-27902
- Plan Check / Job No.
- B22LA18537
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE AT THE 2ND FLOOR FROM DUPLEX TO RESTAURANT: EXISTING 2 STORY BUILDING TO ALLOW EXPANSION OF THE FIRST FLOOR TO SECOND FLOOR AS A COMBINED RESTAURANT USE. ADD INTERIOR STAIRNEW OPEN PATIO DINING AND T.I. WORK ON BOTH FLOORS. parking required utilize AB2097.
- Permit Issued
- Issued on 10/25/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | SAM CHANG |
| Corrections Issued | 9/26/2022 | ALBERT SERVIN |
| Quality Review Completed | 9/29/2022 | PETER KIM |
| Building Plans Picked Up | 10/3/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 10/3/2022 | APPLICANT |
| Applicant returned to address corrections | 11/21/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 12/2/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 1/19/2023 | ALBERT SERVIN |
| Applicant returned to address corrections | 1/20/2023 | ALBERT SERVIN |
| Applicant returned to address corrections | 10/25/2023 | SAM CHANG |
| Applicant returned to address corrections | 1/3/2024 | SAM CHANG |
| Applicant returned to address corrections | 8/6/2024 | SAM CHANG |
| Plan Check Approved | 10/21/2024 | SAM CHANG |
| Issued | 10/25/2024 | APPLICANT |
| CofO in Progress | 1/29/2026 | JEFFREY FULTON |
| No Progress | 2/6/2026 | GREGORY POMISH |
| CofO in Progress | 2/6/2026 | GREGORY POMISH |
| Permit Finaled | 2/9/2026 | JEFFREY DURAN |
| CofO Issued | 2/9/2026 | JEFFREY DURAN |
| Permit Finaled | 2/9/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/4/2022 | YINGSHI HUANG |
| ZA Case | Cleared | 11/4/2022 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 11/16/2022 | COLIN LOREDO |
| DAS Clearance | Cleared | 12/20/2022 | ALBERT SERVIN |
| Food establishment approval | Cleared | 1/24/2023 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 1/31/2023 | PAWAN VERMA |
| Demo/Removal of Rental Units | Cleared | 8/11/2023 | RUZENKA BENEDETTO |
| Tenant Habitability Plan | Cleared | 12/26/2023 | ISMAEL HERNANDEZ |
| SB8 RUD | Cleared | 5/17/2024 | SAMANTHA RIVERA |
| Specific Plan | Cleared | 10/17/2024 | YINGSHI HUANG |
| Specific Plan | Cleared | 10/22/2024 | ALBERT ISAGULIAN |
Contact Information
| Architect | Williams,, Gregory Keith; Lic. No.: C22965 | 1216 N DETROIT STREET APT 5 WEST HOLLYWOOD, CA 90046 |
| Contractor | Urban Lifestyle Group Inc; Lic. No.: 1103744-B | 440 E HUNTINGTON DR #300 ARCADIA, CA 91006 |
| Engineer | Rizk,, Ziad Georges; Lic. No.: C68689 | 12930 EVERMAY CT RANCHO CUCAMONGA, CA 91739 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2024 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Structural Steel Frame | 11/4/2024 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 11/4/2024 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 11/7/2024 | Approved | STEVEN LEVITT |
| Footing/Foundation/Slab | 11/7/2024 | Approved | STEVEN LEVITT |
| Wood Frame | 11/15/2024 | No Access for Inspection | STEVEN LEVITT |
| Wood Frame | 11/21/2024 | Approved | STEVEN LEVITT |
| Drywall Nailing | 11/27/2024 | Approved | STEVEN LEVITT |
| Special/Order Compliance | 12/23/2024 | Partial Approval | JOHN KITCKO |
| Final | 6/13/2025 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 6/13/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 6/18/2025 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 6/18/2025 | Approved | DANIEL VARNUM |
| Final | 1/26/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 1/29/2026 | OK to Issue CofO | JEFFREY FULTON |