4727 N ALLOTT AVE 91423

Certificate Information: 4727 N ALLOTT AVE 91423

Application / Permit
22016-10000-27745
Plan Check / Job No.
B22LA18491
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ENCLOSE (E) 4' X 16'6" COVERED PATIO TO MAKE LIVING AREA FOR THE (E) SFD. INTERIOR REMODEL TO (E) KITCHEN AND LIVING ROOM AND TO REMOVE CEILING AT SECOND FLOOR . ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/2/2022
Issuing Office
Current Status
Issued on 12/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/14/2022 APPLICANT
Assigned to Plan Check Engineer 9/21/2022 OMAR GARNICA
Corrections Issued 9/22/2022 OMAR GARNICA
Plan Check Approved 10/25/2022 OMAR GARNICA
Issued 12/2/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/4/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 10/4/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 10/4/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 10/4/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 10/4/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Cp Builder Inc; Lic. No.: 1072560-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/15/2022 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 1/18/2023 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 2/6/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 2/7/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/24/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 3/24/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 3/24/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 3/24/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/18/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/18/2023 Approved MISAEL ESPARZA
Green Building Rough 4/18/2023 Approved MISAEL ESPARZA
HVAC-Rough 4/18/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 4/18/2023 Approved MISAEL ESPARZA
Insulation 5/16/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 5/13/2024 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 5/13/2024 Corrections Issued MISAEL ESPARZA