1091 S HOOVER ST 90006

Certificate Information: 1091 S HOOVER ST 90006

Application / Permit
22016-10000-27731
Plan Check / Job No.
B22LA18485
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
EXISTING RETAIL BUILDING: INSTALLATION OF NEW CONDENSER UNIT AND IT'S PLATFORM ON THE ROOF TO REPLACE THE OLD UNIT IN THE MACHINE ROOM ON THE MEZZANINE LEVEL. NEW COLUMNS AND PAD FOOTINGS.
Permit Issued
Issued on 12/29/2022
Issuing Office
Metro
Current Status
Issued on 12/29/2022

Permit Application Status History

Submitted 9/14/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 ALBERT SERVIN
Corrections Issued 9/20/2022 ALBERT SERVIN
Quality Review Completed 9/22/2022 PETER KIM
Building Plans Picked Up 9/28/2022 APPLICANT
Disabled Access Plans Picked Up 11/10/2022 APPLICANT
Plan Check Approved 12/15/2022 ALBERT SERVIN
Issued 12/29/2022 APPLICANT

Permit Application Clearance Information

DAS Clearance Cleared 12/14/2022 ALBERT SERVIN

Contact Information

Contractor Complete Construction Services Inc; Lic. No.: 970215-B 6201 SERENA PLACE      RANCHO CUCAMONGA, CA 91737
Engineer Baroonian,, Armen; Lic. No.: S4227 867 N FAIR OAKS AVE 100      PASADENA, CA 91103

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/13/2023 Approved RAMAZANALI ALMASI
Deputy Drilled-In Anchors 1/20/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/23/2023 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 1/23/2023 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 1/24/2023 Partial Inspection KATY RAMIREZ
Wood Frame 2/16/2023 Approved RAMAZANALI ALMASI