249 S CORONADO ST 9-10 90057

Certificate Information: 249 S CORONADO ST 9-10 90057

Application / Permit
22016-10000-27628
Plan Check / Job No.
B22LA18426
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EX. STORAGE INTO TWO ACCESSORY DWELLING UNITS ( UNIT #9 AND #10 ) FOR EX. 8-UNIT APARTMENT PER GCS 65852.2(e)(1)(C).
Permit Issued
Issued on 4/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2022 APPLICANT
Assigned to Plan Check Engineer 9/16/2022 LUKE GONZALES
Corrections Issued 9/17/2022 LUKE GONZALES
Building Plans Picked Up 9/22/2022 APPLICANT
Applicant returned to address corrections 10/18/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 10/24/2022 MIROOSH KHACHATOORIAN
Plan Check Approved 12/28/2022 ROSENDO MEDINA
Issued 4/14/2023 APPLICANT
CofO in Progress 5/7/2024 JEROME BLACKWOOD
CofO Issued 5/16/2024 RAFAEL ESPINOZA
Permit Finaled 5/16/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 10/26/2022 TREVOR QUAN
Sewer availability Cleared 10/26/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 10/31/2022 TREVOR QUAN
Tenant Habitability Plan Cleared 12/28/2022 BRIAN ANGAMI

Contact Information

Contractor Turnaround Construction; Lic. No.: 1048883-B 14103 BRIGHTON AVENUE      GARDENA, CA 90249

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/21/2023 Corrections Issued RAMAZANALI ALMASI
Footing/Foundation/Slab 7/17/2023 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 7/21/2023 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 8/1/2023 Approved RAMAZANALI ALMASI
Insulation 10/3/2023 Not Ready for Inspection RAMAZANALI ALMASI
Insulation 10/11/2023 Partial Approval RAMAZANALI ALMASI
Green Building Rough 10/31/2023 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Rough 10/31/2023 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 10/31/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Rough 11/7/2023 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Rough 11/7/2023 Partial Approval JEROME BLACKWOOD
Wood Frame 11/7/2023 Not Ready for Inspection JEROME BLACKWOOD
Insulation 11/8/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 11/22/2023 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 11/27/2023 Partial Approval JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 2/27/2024 SGSOV Not Ready JEROME BLACKWOOD
Final 3/7/2024 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 3/7/2024 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 3/7/2024 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Final 3/7/2024 Approved JEROME BLACKWOOD
METHANE-Rough 3/7/2024 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Not Ready JEROME BLACKWOOD
Smoke Detectors 3/7/2024 Approved JEROME BLACKWOOD
Wood Frame 3/7/2024 Partial Approval JEROME BLACKWOOD
Final 4/15/2024 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 4/15/2024 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 4/15/2024 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV Approved JEROME BLACKWOOD
Wood Frame 4/15/2024 Partial Approval JEROME BLACKWOOD
Final 4/18/2024 Corrections Issued JEROME BLACKWOOD
Green Building Final 4/18/2024 Approved JEROME BLACKWOOD
Green Building Rough 4/18/2024 Approved JEROME BLACKWOOD
Wood Frame 4/18/2024 Approved JEROME BLACKWOOD
Final 4/25/2024 Partial Approval JEROME BLACKWOOD
Final 5/6/2024 OK to Issue CofO JEROME BLACKWOOD