359 N AVENUE 52 90042
Certificate Information: 359 N AVENUE 52 90042
- Application / Permit
- 22016-10000-27567
- Plan Check / Job No.
- B22LA18371
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODELING OF EXISING SFD.
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/25/2024
Permit Application Status History
| Submitted | 9/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2022 | JOE VO |
| Corrections Issued | 9/20/2022 | JOE VO |
| Plan Check Approved | 5/18/2023 | JOE VO |
| Issued | 6/2/2023 | APPLICANT |
| Permit Finaled | 7/24/2024 | CRAIG VAUGHAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/28/2022 | KIRK LINKLATER |
| HPOZ | Cleared | 5/11/2023 | MAX LODER |
| Historic monument | Cleared | 5/11/2023 | MAX LODER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/22/2023 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/22/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 8/10/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/21/2023 | Approved | OSVALDO PARAMO |
| Gas Test | 8/21/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 8/21/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Gas Test | 3/5/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 3/5/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/5/2024 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 3/14/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/14/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/18/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Shower Pan | 3/18/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/21/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/21/2024 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/21/2024 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 3/21/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/26/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/26/2024 | Approved | HAMIK HARTOUNIAN |
| Insulation | 3/29/2024 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/4/2024 | Approved | BRIAN SULLIVAN |
| Final | 7/11/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 7/17/2024 | Corrections Issued | BRENDAN MORELLI |
| Final | 7/17/2024 | Corrections Issued | BRENDAN MORELLI |
| Gas Test | 7/17/2024 | Approved | BRENDAN MORELLI |
| HVAC-Final | 7/17/2024 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 7/17/2024 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 7/17/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/24/2024 | Approved | CRAIG VAUGHAN |
| Final | 7/24/2024 | Permit Finaled | CRAIG VAUGHAN |
| HVAC-Final | 7/24/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 7/24/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 7/24/2024 | SGSOV Approved | CRAIG VAUGHAN |